Bürkert Fluid Control Systems’ new multi-million dollar campus will feature a new 168,000-square foot facility located on a 98-acre parcel of wooded forest and farmland in Huntersville, North Carolina. The campus features administrative areas, manufacturing space and an indoor fitness center with a basketball court.  As the company continues to grow, the design allows the space for additional construction in the future.   The facility is designed by WHN+ Architects and EDIFICE, Inc. will manage the construction.

EDIFICE is pleased to be selected to participate in the growth of Bürkert USA. Our intentions with this project blog, is to provide monthly updates on the construction progress and share this experience as the project develops.

Bürkert USA

Bürkert: North American HQ | April 2016

Posted on Apr 12th, 2016 - By Megan Asher - 0 Comments

Project Update: The interior finishes are progressing well. The painting and ceiling grid are complete in the front office areas and are…

Read More →

Bürkert

Bürkert: North American HQ | March 2016

Posted on Mar 11th, 2016 - By Megan Asher - 0 Comments

Project Update: It has been a busy couple of months and the building is coming together well. The front interior office area has the…

Read More →

Bürkert

Bürkert: North American HQ | January 2016

Posted on Jan 14th, 2016 - By Megan Asher - 0 Comments

Project Update: Progress to the Bürkert USA Headquarters continues, as Edifice was able to get the TPO roofing completed on the warehouse…

Read More →

Bürkert

Bürkert: North American HQ | December 2015

Posted on Dec 8th, 2015 - By Megan Asher - 0 Comments

Project Update: Big strides were made at the Bürkert project with the completion of the exterior during the month of November. The…

Read More →

Bürkert

Bürkert: North American HQ | November 2015

Posted on Nov 9th, 2015 - By Megan Asher - 0 Comments

Project Update: Despite the gloomy weather the Bürkert building progressed well during October. The structural steel and roof deck…

Read More →

Bürkert_October

Bürkert: North American HQ | October 2015

Posted on Oct 9th, 2015 - By Megan Asher - 0 Comments

Project Update: In early September the slab on grade pours were completed and the steel erection was in full effect.  The entire front…

Read More →

Bürkert Concrete

Bürkert: North American HQ | September 2015

Posted on Sep 7th, 2015 - By Megan Asher - 0 Comments

Project Update: Early August started out with a heavy emphasis on plumbing and electrical underground within the slab areas. Despite a…

Read More →

Bürkert: North American HQ | August 2015

Posted on Aug 12th, 2015 - By Megan Asher - 0 Comments

Project Update: With the receipt of the foundation permit on July 10, 2015, Edifice Inc. and Lithko Concrete Contracting, Inc. (Concrete…

Read More →

Bürkert: North American HQ | June 2015

Posted on Jun 9th, 2015 - By Megan Asher - 0 Comments

Project Update: The site is taking shape with the erosion control measures and skimmer basins in place. Since receiving the approval to…

Read More →

Burkert: North American HQ | May 2015

Posted on Apr 30th, 2015 - By Megan Asher - 0 Comments

Project Update: The Burkert project has taken off with full steam since the groundbreaking late last month. A pre-construction meeting…