Project Update:Click Here to view the live construction cam feed!

The site is taking shape with the erosion control measures and skimmer basins in place. Since receiving the approval to grade from Huntersville in early May, the mass grading is almost completed with the front office area on grade and just a little bit of fill remaining at the warehouse area.

The weather was on our side this month with rain affecting the site work for only a couple days near the end of May.

On the horizon for next month, we plan to finish grading the building pad, parking lot and entrance drive. Once the building permit is received, Edifice will move forward with building foundations and site utilities.

Building pad site grading 5.27.15

View from above Oak Trees 5.29.15. Building pad to upper left of dump trucks.

Overall site - Erosion control fencing, topsoil stock pile, and building pad grading.

Overall building area looking East.

Workers taking lunch under the newly trimmed Oak Trees at the picnic area.