Project Update:

It has been a busy couple of months and the building is coming together well. The front interior office area has the mechanical, electrical, and plumbing work completed and the sheetrock has been hung. Coatings 2000 has started priming the office walls and painting the open ceilings. The massive promenade area has also been hung and sheetrock finishing is underway. In the warehouse area, mechanical and electrical rough-in continues with much of the larger spiral duct-work now complete. Much of the focus for the mechanical has switched to the main equipment-piping in the mechanical room as well as tie-in of all the roof-top units. In the same token, much of the electrical work has focused on the main feeds and gear. With the dryer weather some of the site grading was finished up as well as the first layer of asphalt on the heavy duty North drive.