Project Update:

In early September the slab on grade pours were completed and the steel erection was in full effect.  The entire front office area was erected, and despite the weekend weather, courtesy of Hurricane Joaquin, Edifice managed to make the 2nd floor office area pour on October 6th.  Erection of the structural steel in the warehouse area is also well underway. Other work for the month included progress with installing the underground chiller piping, the underground rough-in for the main electrical room, and the start of the plumbing rough-in for the group bathrooms in the office area.

In regards to the site, Horsepower Site Service, LLC proactively placed the stone needed for the curb and south lot areas prior to the heavy rain. This allowed for uninterrupted site access for employee parking and helped maintain site safety.