Project Update:

Early August started out with a heavy emphasis on plumbing and electrical underground within the slab areas. Despite a couple of tough weeks in Mid-August, due to heavy isolated afternoon thunderstorms affecting progress, August finished off strong. Over the last two weeks of August, Lithko Contracting, Inc. placed more than 90,000 SF and 1,525 CU YDS of concrete slab on grade.  Other building work included construction of the cast in place elevator shaft and the start of steel erection.

The site work is also coming along on schedule. Horsepower Site Service, LLC completed the majority of the underground storm drainage along with installing the water lines. The Bürkert portion of the road widening on Mount Holly-Huntersville road is also nearing completion.