Construction Highlights Last 30 Days:

  • Hung the Sound Wall in Area C
  • Elevator #4 Substantial Completion
  • Applied Primer, Point and the First Coat of Paint on Level 01 of Area C and Level 02 of Area A/B
  • Installed Ceiling Grid on Level 01 of Area C and in Classrooms on Level 03/02
  • Began to Install the Ceiling Grids in the Hallways on Level 03/02
  • Hung and Finished the Drywall on Level 02 of Area C and Level 01 of Area A/B
  • Roughed In Above Ceiling (Before Grid) on Levels 01 & 02 of Area C
  • Completed Hard Ceiling Inspections on Level 01 of Area C – SCO Inspection 12/08/14
  • Continued to Rough In the ACT Above Ceiling on Level 01 of Area C
  • Started Framing the North Canopy
  • Installed Metal Panels in Lobby
  • Completed the Overhead Rough In at Lobby Ceiling
  • Continued to Laminate and Finish the Walls of the House on Level 01
  • Completed Balcony Ceiling Rough In and Grid on Level 01 of Lobby – SCO Inspection 12/08/14
  • Completed Balcony Ceiling Rough In and Grid on Level 02 of Lobby – SCO Inspection 12/15/14
  • Completed Orchestra Shell Ceiling Framing and Rough In – SCO Inspection 12/08/14
  • Continued to Finish and Paint the House Walls on All Levels of Area D
  • Began to Rough In the Balcony Ceiling on Level 03
  • Poured Stair G Pans
  • Continued Framing the East Lobby Wall
  • Completed Roofing at Bottle Opener
  • Continued Installing the ACM Metal Panels
  • Nearing Completion on Framing the SLL Hallway Walls of Level 03
  • Started to Frame the SLL Hallway Walls on Levels 01 & 02
  • Continued to Hang and Finish the Walls in the Pre-function Space on Level 01 and Framed the Walls in the Pre-function Space on Level 02
  • Completed Overhead Rough / Ceiling Grid Inspections on Level 02 of Area A/B – LS3P Inspection 12/08/12
  • Began to Apply the Primer, Point Up and the First Coat of Paint on Level 01 of Area A/B
  • Continued to Apply the Block Fill to the CMU Walls in the Back of the House – Area B
  • Installed the AHU and Duct Work in the D02 Mechanical Room
  • Completed the Hanover Concrete Sidewalks
  • Continued Progress on the 2nd Street Concrete Sidewalk and Curb
  • Installed the Aluminum/Hollow Metal Swinging Doors
  • Completed the Installation of the Curtainwall/Storefront Glass
  • Began the Landscaping of the Courtyard
Update for December 2014

Monthly Photo Highlights Include:

North Lobby ACM Metal PanelsNorthLobbyCollage

Monumental Stair
Monumental-Stair-Poured

South Lobby Entrance
South-Lobby-Entrance-Curtainwall

Followspot Lighting in House
Followspot

House Walls
HouseWalls_Colllage

Hanging and Finishing the Walls in the Pre-Function Spaces, Classrooms, and Studio
Wall_Collage

Courtyard Curtain WallCourtyard-Curtainwall_2

Project Aerial: December 15, 2014
DecemberAerial