Project Update: October 2014

Construction Highlights Last 30 Days:

  • Completed Roofing
  • Veneer on Building Completed
  • Utility Work Completed
  • Walls Hung and Finished Area A/B Level 02/03
  • Walls Hung and Finished Area C Level 01
  • Wall Framing Complete Area C Level 02 & Area A/B Level 01
  • Upper House Framing & Painting Complete
  • Painting Started on Stage & Back of House Areas
  • Metal Panels on North Side of House 50%
  • Metal Panels on Stair F 100%
  • Sheathing on Lobby Overhang 100%
  • Permanent Power On

Monthly Photo Highlights Include:

West Exterior Progress West-Exterior-Progress

Progress on Stair F & Lobby Stair-F-&-Lobby-Progress

Monumental Stair in Lobby Monumental-Stair-In-Lobby

Finishing Walls in Areas A & B Finishing-Walls-In-Area-A-&-B

Curb Installation on Hanover Curb-Install-On-Hanover

Project Aerial: October 15, 2014
DSC_0569

Share This

Quick Links

In the News


Play Button CrossRidge Building One | February 2021

CrossRidge Building One | February 2021

The CrossRidge Office Building One is moving right along! This month’s video features finalizing the slab finish after a morning...
EDIFICE Promotes Gaius Carter to Project Executive

EDIFICE Promotes Gaius Carter to Project Executive

EDIFICE is pleased to announce that Gaius Carter has been promoted to Project Executive focusing on the manufacturing sector. Gaius has...
The John Crosland School Takes Learning in a New Direction

The John Crosland School Takes Learning in a New Direction

EDIFICE, along with a group of great partners, helped bring the John Crosland School’s outdoor pavilion to life.  Watch how...