Project Update: October 2014

Construction Highlights Last 30 Days:

  • Completed Roofing
  • Veneer on Building Completed
  • Utility Work Completed
  • Walls Hung and Finished Area A/B Level 02/03
  • Walls Hung and Finished Area C Level 01
  • Wall Framing Complete Area C Level 02 & Area A/B Level 01
  • Upper House Framing & Painting Complete
  • Painting Started on Stage & Back of House Areas
  • Metal Panels on North Side of House 50%
  • Metal Panels on Stair F 100%
  • Sheathing on Lobby Overhang 100%
  • Permanent Power On

Monthly Photo Highlights Include:

West Exterior Progress West-Exterior-Progress

Progress on Stair F & Lobby Stair-F-&-Lobby-Progress

Monumental Stair in Lobby Monumental-Stair-In-Lobby

Finishing Walls in Areas A & B Finishing-Walls-In-Area-A-&-B

Curb Installation on Hanover Curb-Install-On-Hanover

Project Aerial: October 15, 2014
DSC_0569

Share This

Quick Links

In the News


Dorchester County Economic Development Commences Construction with a Groundbreaking Ceremony for New Commerce Center in Summerville

Dorchester County Economic Development Commences Construction with a Groundbreaking Ceremony for New Commerce Center in Summerville

SUMMERVILLE, S.C. (November 16, 2022) – Dorchester County Economic Development held a groundbreaking ceremony earlier this week to commence construction...
City of Statesville breaks ground on the new Fire Station

City of Statesville breaks ground on the new Fire Station

(Statesville, NC) City leaders and fire department personnel broke ground for the new Fire Station One on Wednesday, November 30...
Prost to our 2022 Fall Party | Oktoberfeier!

Prost to our 2022 Fall Party | Oktoberfeier!

After a 2 year break (thanks COVID) Oktoberfeier returned. Just as the seasons started to change and with fall in...