Project Update: October 2014

Construction Highlights Last 30 Days:

  • Completed Roofing
  • Veneer on Building Completed
  • Utility Work Completed
  • Walls Hung and Finished Area A/B Level 02/03
  • Walls Hung and Finished Area C Level 01
  • Wall Framing Complete Area C Level 02 & Area A/B Level 01
  • Upper House Framing & Painting Complete
  • Painting Started on Stage & Back of House Areas
  • Metal Panels on North Side of House 50%
  • Metal Panels on Stair F 100%
  • Sheathing on Lobby Overhang 100%
  • Permanent Power On

Monthly Photo Highlights Include:

West Exterior Progress West-Exterior-Progress

Progress on Stair F & Lobby Stair-F-&-Lobby-Progress

Monumental Stair in Lobby Monumental-Stair-In-Lobby

Finishing Walls in Areas A & B Finishing-Walls-In-Area-A-&-B

Curb Installation on Hanover Curb-Install-On-Hanover

Project Aerial: October 15, 2014
DSC_0569

Share This

Quick Links

In the News


Live Feed: CMPD Central Division Facility

Live Feed: CMPD Central Division Facility

Follow along with the construction progress, via recent snapshot or a time-lapse, at Charlotte-Mecklenburg Police Department’s new Central Division Facility.
Huber_Technology_groundbreaking

Wastewater equipment manufacturer breaks ground on new HQ in Charlotte region

Look for Huber Technology Inc. to open its relocated headquarters in Lincoln County by early 2020 or potentially earlier —...
Edifice continues its support of Covenant Day and the ContainIt Project

Edifice continues its support of Covenant Day and the ContainIt Project

Edifice continues its support of Covenant Day as a key sponsor of their annual Sustainability Sporting Clay Shoot benefiting the ContainIt...