Project Update: October 2014

Construction Highlights Last 30 Days:

  • Completed Roofing
  • Veneer on Building Completed
  • Utility Work Completed
  • Walls Hung and Finished Area A/B Level 02/03
  • Walls Hung and Finished Area C Level 01
  • Wall Framing Complete Area C Level 02 & Area A/B Level 01
  • Upper House Framing & Painting Complete
  • Painting Started on Stage & Back of House Areas
  • Metal Panels on North Side of House 50%
  • Metal Panels on Stair F 100%
  • Sheathing on Lobby Overhang 100%
  • Permanent Power On

Monthly Photo Highlights Include:

West Exterior Progress West-Exterior-Progress

Progress on Stair F & Lobby Stair-F-&-Lobby-Progress

Monumental Stair in Lobby Monumental-Stair-In-Lobby

Finishing Walls in Areas A & B Finishing-Walls-In-Area-A-&-B

Curb Installation on Hanover Curb-Install-On-Hanover

Project Aerial: October 15, 2014
DSC_0569

Share This

Quick Links

In the News


Play Button Metrolina Park | August 2018

Metrolina Park | August 2018

The Metrolina Park has reached completion with buildings 1-5 successfully constructed and turned over to the owner / developer, Beacon...
The Charlotte Business Journal honors Edifice as the #1 Middle Market Leader

The Charlotte Business Journal honors Edifice as the #1 Middle Market Leader

The Charlotte Business Journal honored local middle market firms for propelling the region’s economy. In honoring these companies, the Business...
Wing_Haven

Wing Haven’s SEED Wildlife Garden Comes to Life

As a long-time supporter of Wing Haven Garden, Edifice was pleased to play a small role in bringing Wing Haven’s...