Project Update: October 2014

Construction Highlights Last 30 Days:

  • Completed Roofing
  • Veneer on Building Completed
  • Utility Work Completed
  • Walls Hung and Finished Area A/B Level 02/03
  • Walls Hung and Finished Area C Level 01
  • Wall Framing Complete Area C Level 02 & Area A/B Level 01
  • Upper House Framing & Painting Complete
  • Painting Started on Stage & Back of House Areas
  • Metal Panels on North Side of House 50%
  • Metal Panels on Stair F 100%
  • Sheathing on Lobby Overhang 100%
  • Permanent Power On

Monthly Photo Highlights Include:

West Exterior Progress West-Exterior-Progress

Progress on Stair F & Lobby Stair-F-&-Lobby-Progress

Monumental Stair in Lobby Monumental-Stair-In-Lobby

Finishing Walls in Areas A & B Finishing-Walls-In-Area-A-&-B

Curb Installation on Hanover Curb-Install-On-Hanover

Project Aerial: October 15, 2014
DSC_0569

Share This

Quick Links

In the News


Play Button The Square at South End | September 2020

The Square at South End | September 2020

The Square at South End continues to impress. The parking deck structure is complete and the site cleared around it...
Charleston Team

Edifice Expands to Charleston

Edifice, the regional general contractor headquartered in Charlotte, NC, expanded its operations and opened an office in Charleston. The company...
PatsPlaceBBQ

BBQ for a Great Cause | Supporting Pat’s Place Child Advocacy Center

BBQ & Blue Jeans is the party of the summer and the signature annual fundraising event for Pat’s Place Child...