Project Update: October 2014

Construction Highlights Last 30 Days:

  • Completed Roofing
  • Veneer on Building Completed
  • Utility Work Completed
  • Walls Hung and Finished Area A/B Level 02/03
  • Walls Hung and Finished Area C Level 01
  • Wall Framing Complete Area C Level 02 & Area A/B Level 01
  • Upper House Framing & Painting Complete
  • Painting Started on Stage & Back of House Areas
  • Metal Panels on North Side of House 50%
  • Metal Panels on Stair F 100%
  • Sheathing on Lobby Overhang 100%
  • Permanent Power On

Monthly Photo Highlights Include:

West Exterior Progress West-Exterior-Progress

Progress on Stair F & Lobby Stair-F-&-Lobby-Progress

Monumental Stair in Lobby Monumental-Stair-In-Lobby

Finishing Walls in Areas A & B Finishing-Walls-In-Area-A-&-B

Curb Installation on Hanover Curb-Install-On-Hanover

Project Aerial: October 15, 2014
DSC_0569

Share This

Quick Links

In the News


Play Button The Square at South End has reached the Top

The Square at South End has reached the Top

We’ve topped out! The Square at South End has reached a major milestone in the life of this construction project...
How COVID-19 is Impacting Charlotte’s Commercial Real Estate Market

How COVID-19 is Impacting Charlotte’s Commercial Real Estate Market

Cranes and construction crews are still largely in full swing in Charlotte, despite the earth-shattering impacts of the coronavirus pandemic...
Thank you field Personnel

Thank you EDIFICE Field Personnel

Your courage and dedication during COVID-19 goes above and beyond.   In our community, construction has been considered an essential...