Covenant Day School | October 2015

Project Update:Click Here to view the live construction cam feed!

On site at the Covenant Day School, we have completed all of the building footings and the retaining wall at the NW corner. All of the slab rough-ins are completed and we are currently preparing the slab to pour on 10/23. On October 14th, we received our first delivery of steel!

Covenant Day SchoolThe steel erection has since begun for Phase 1 and will be completed in about 8-10 days. Phase 2 will begin immediately following our slab pour on Friday. The building structure should be completely erected by mid November.  In anticipation for the upcoming topping out ceremony, parents, alumni, students and teachers all signed the final beams to be placed (pictured left).

The fitness center was officially completed last week. With the keys turned over, a ribbon cutting ceremony was held last Friday.

 

 

 

Covenant Day School Monthly Photo Highlights:

Click on the photos below to view the full photo.

[hover_pack img=”https://edificeinc.com/wp-content/uploads/2015/10/Image-9-16-15-5.48.07-AM.jpg” link=”https://edificeinc.com/wp-content/uploads/2015/10/Image-9-16-15-5.48.07-AM.jpg” width=”300″ height=”225″ opacity=”70″ text=”The team working hard with a 3:30am concrete pour” text_slide=”from-bottom”]

[hover_pack img=”https://edificeinc.com/wp-content/uploads/2015/10/Image-9-17-15-5.48.24-PM.jpg” link=”https://edificeinc.com/wp-content/uploads/2015/10/Image-9-17-15-5.48.24-PM.jpg” width=”300″ height=”225″ opacity=”70″ text=”A job well done!” text_slide=”from-bottom”]

[hover_pack img=”https://edificeinc.com/wp-content/uploads/2015/10/Image-9-18-15-2.34.15-PM.jpg” link=”https://edificeinc.com/wp-content/uploads/2015/10/Image-9-18-15-2.34.15-PM.jpg” width=”225″ height=”300″ opacity=”70″]

[hover_pack img=”https://edificeinc.com/wp-content/uploads/2015/10/Image-10-14-15-2.34.19-PM.jpg” link=”https://edificeinc.com/wp-content/uploads/2015/10/Image-10-14-15-2.34.19-PM.jpg” width=”374″ height=”300″ opacity=”70″]

[hover_pack img=”https://edificeinc.com/wp-content/uploads/2015/10/FitnessCenter2.jpg” link=”https://edificeinc.com/wp-content/uploads/2015/10/FitnessCenter2.jpg” width=”374″ height=”300″ opacity=”70″ text=”The Ribbon Cutting ceremony for the Fitness Center held October 16, 2015. {Photo courtesy of Covenant Day School}” text_slide=”from-bottom”]

[hover_pack img=”https://edificeinc.com/wp-content/uploads/2015/10/FitnessCenterFinal.jpg” link=”https://edificeinc.com/wp-content/uploads/2015/10/FitnessCenterFinal.jpg” width=”225″ height=”300″ opacity=”70″   text=”The equipment ready to be used in the fitness center. {Photo courtesy of Covenant Day School}” text_slide=”from-bottom”]

 

Stay on top industry news with edifice

Pineville Town Hall and Library: Award-Winning Community Transformation

Pineville Town Hall and Library: Award-Winning Community Transformation

Have you ever wondered how a single construction project can transform an entire community? The Pineville Town Hall and Library...
Celebrating Eric Laster’s Legacy and Retirement

Celebrating Eric Laster’s Legacy and Retirement

On December 13, 2024, Edifice Construction gathered at the prestigious Quail Hollow Country Club in Charlotte, NC, to honor a...
Lil’ Tykes Christmas Party: A Grinchmas Celebration

Lil’ Tykes Christmas Party: A Grinchmas Celebration

On Saturday, December 7th, Edifice families gathered for our annual Lil’ Tykes Christmas Party at the Barn at Marvin Efird...