On site at the Covenant Day School, we have completed all of the building footings and the retaining wall at the NW corner. All of the slab rough-ins are completed and we are currently preparing the slab to pour on 10/23. On October 14th, we received our first delivery of steel!

Covenant Day SchoolThe steel erection has since begun for Phase 1 and will be completed in about 8-10 days. Phase 2 will begin immediately following our slab pour on Friday. The building structure should be completely erected by mid November.  In anticipation for the upcoming topping out ceremony, parents, alumni, students and teachers all signed the final beams to be placed (pictured left).

The fitness center was officially completed last week. With the keys turned over, a ribbon cutting ceremony was held last Friday.

 

 

 

Covenant Day School Monthly Photo Highlights:

Click on the photos below to view the full photo.

The team working hard with a 3:30am concrete pour

A job well done!

The Ribbon Cutting ceremony for the Fitness Center held October 16, 2015. {Photo courtesy of Covenant Day School}