Covenant Day School | October 2015

Project Update:Click Here to view the live construction cam feed!

On site at the Covenant Day School, we have completed all of the building footings and the retaining wall at the NW corner. All of the slab rough-ins are completed and we are currently preparing the slab to pour on 10/23. On October 14th, we received our first delivery of steel!

Covenant Day SchoolThe steel erection has since begun for Phase 1 and will be completed in about 8-10 days. Phase 2 will begin immediately following our slab pour on Friday. The building structure should be completely erected by mid November.  In anticipation for the upcoming topping out ceremony, parents, alumni, students and teachers all signed the final beams to be placed (pictured left).

The fitness center was officially completed last week. With the keys turned over, a ribbon cutting ceremony was held last Friday.

 

 

 

Covenant Day School Monthly Photo Highlights:

Click on the photos below to view the full photo.

[hover_pack img=”https://edificeinc.com/wp-content/uploads/2015/10/Image-9-16-15-5.48.07-AM.jpg” link=”https://edificeinc.com/wp-content/uploads/2015/10/Image-9-16-15-5.48.07-AM.jpg” width=”300″ height=”225″ opacity=”70″ text=”The team working hard with a 3:30am concrete pour” text_slide=”from-bottom”]

[hover_pack img=”https://edificeinc.com/wp-content/uploads/2015/10/Image-9-17-15-5.48.24-PM.jpg” link=”https://edificeinc.com/wp-content/uploads/2015/10/Image-9-17-15-5.48.24-PM.jpg” width=”300″ height=”225″ opacity=”70″ text=”A job well done!” text_slide=”from-bottom”]

[hover_pack img=”https://edificeinc.com/wp-content/uploads/2015/10/Image-9-18-15-2.34.15-PM.jpg” link=”https://edificeinc.com/wp-content/uploads/2015/10/Image-9-18-15-2.34.15-PM.jpg” width=”225″ height=”300″ opacity=”70″]

[hover_pack img=”https://edificeinc.com/wp-content/uploads/2015/10/Image-10-14-15-2.34.19-PM.jpg” link=”https://edificeinc.com/wp-content/uploads/2015/10/Image-10-14-15-2.34.19-PM.jpg” width=”374″ height=”300″ opacity=”70″]

[hover_pack img=”https://edificeinc.com/wp-content/uploads/2015/10/FitnessCenter2.jpg” link=”https://edificeinc.com/wp-content/uploads/2015/10/FitnessCenter2.jpg” width=”374″ height=”300″ opacity=”70″ text=”The Ribbon Cutting ceremony for the Fitness Center held October 16, 2015. {Photo courtesy of Covenant Day School}” text_slide=”from-bottom”]

[hover_pack img=”https://edificeinc.com/wp-content/uploads/2015/10/FitnessCenterFinal.jpg” link=”https://edificeinc.com/wp-content/uploads/2015/10/FitnessCenterFinal.jpg” width=”225″ height=”300″ opacity=”70″   text=”The equipment ready to be used in the fitness center. {Photo courtesy of Covenant Day School}” text_slide=”from-bottom”]

 

Share This

Quick Links

Stay on top industry news with edifice

8 people with shovels digging in a ground breaking ceremony. Two large pieces of construction equipment are behind them. Between the equipment is a large banner with a computer rendering of the project on it.

HEYCO-Werk USA Breaks Ground on Manufacturing Facility in Gaston County

CHARLOTTE, N.C. (June 18, 2024) – HEYCO-Werk USA celebrated the start of construction of their new US manufacturing facility with...
EDIFICE Construction Ranks as a TOP General Contractor in Charleston Area

EDIFICE Construction Ranks as a TOP General Contractor in Charleston Area

We are thrilled to announce that EDIFICE Construction has achieved a remarkable milestone by securing the #8 spot in the...
Continental Tire Unveils Expanded Americas HQ in Lancaster County

Continental Tire Unveils Expanded Americas HQ in Lancaster County

Continental Tire the Americas has significantly expanded its Lancaster County headquarters operations. The tire giant yesterday unveiled its new, 90,000-square-foot...