Covenant Day School | October 2015

Project Update:Click Here to view the live construction cam feed!

On site at the Covenant Day School, we have completed all of the building footings and the retaining wall at the NW corner. All of the slab rough-ins are completed and we are currently preparing the slab to pour on 10/23. On October 14th, we received our first delivery of steel!

Covenant Day SchoolThe steel erection has since begun for Phase 1 and will be completed in about 8-10 days. Phase 2 will begin immediately following our slab pour on Friday. The building structure should be completely erected by mid November.  In anticipation for the upcoming topping out ceremony, parents, alumni, students and teachers all signed the final beams to be placed (pictured left).

The fitness center was officially completed last week. With the keys turned over, a ribbon cutting ceremony was held last Friday.

 

 

 

Covenant Day School Monthly Photo Highlights:

Click on the photos below to view the full photo.

[hover_pack img=”https://edificeinc.com/wp-content/uploads/2015/10/Image-9-16-15-5.48.07-AM.jpg” link=”https://edificeinc.com/wp-content/uploads/2015/10/Image-9-16-15-5.48.07-AM.jpg” width=”300″ height=”225″ opacity=”70″ text=”The team working hard with a 3:30am concrete pour” text_slide=”from-bottom”]

[hover_pack img=”https://edificeinc.com/wp-content/uploads/2015/10/Image-9-17-15-5.48.24-PM.jpg” link=”https://edificeinc.com/wp-content/uploads/2015/10/Image-9-17-15-5.48.24-PM.jpg” width=”300″ height=”225″ opacity=”70″ text=”A job well done!” text_slide=”from-bottom”]

[hover_pack img=”https://edificeinc.com/wp-content/uploads/2015/10/Image-9-18-15-2.34.15-PM.jpg” link=”https://edificeinc.com/wp-content/uploads/2015/10/Image-9-18-15-2.34.15-PM.jpg” width=”225″ height=”300″ opacity=”70″]

[hover_pack img=”https://edificeinc.com/wp-content/uploads/2015/10/Image-10-14-15-2.34.19-PM.jpg” link=”https://edificeinc.com/wp-content/uploads/2015/10/Image-10-14-15-2.34.19-PM.jpg” width=”374″ height=”300″ opacity=”70″]

[hover_pack img=”https://edificeinc.com/wp-content/uploads/2015/10/FitnessCenter2.jpg” link=”https://edificeinc.com/wp-content/uploads/2015/10/FitnessCenter2.jpg” width=”374″ height=”300″ opacity=”70″ text=”The Ribbon Cutting ceremony for the Fitness Center held October 16, 2015. {Photo courtesy of Covenant Day School}” text_slide=”from-bottom”]

[hover_pack img=”https://edificeinc.com/wp-content/uploads/2015/10/FitnessCenterFinal.jpg” link=”https://edificeinc.com/wp-content/uploads/2015/10/FitnessCenterFinal.jpg” width=”225″ height=”300″ opacity=”70″   text=”The equipment ready to be used in the fitness center. {Photo courtesy of Covenant Day School}” text_slide=”from-bottom”]

 

Share This

Quick Links

In the News


Play Button Eastway Recreation Center Project Update | September 2019

Eastway Recreation Center Project Update | September 2019

Another Eastway project update for you! Not that we’re biased, but it’s looking 💯
Pastors Masters 2019 at The Club at Longview

Pastors Masters 2019 at The Club at Longview

This year’s tournament got off to a chilly start as we returned back to The Club at Longview and the...
Edifice_Oktoberfeier_2019

Prost to our 2019 Fall Party | Oktoberfeier!

Fall is officially here and we celebrated the change of seasons with our annual German festival, Oktoberfeier. Saturday, September 28...