Metrolina Park | January 2017

Despite some weather activity early January, Building #1 is moving right along with the completion of steel erection and ongoing roofing activities. Electrical, Mechanical and Plumbing crews are all on site and roughing in. Exterior patching is complete and the building is ready for paint.
Building #2 slab is almost complete with 9 of the 12 slabs in place. The first set of panels were poured in place and ready to stand. The park continues to take shape as we have made great progress on site utilities and roads. Grading activities also continue at lots 3-6.

Share This

Quick Links

Stay on top industry news with edifice

8 people with shovels digging in a ground breaking ceremony. Two large pieces of construction equipment are behind them. Between the equipment is a large banner with a computer rendering of the project on it.

HEYCO-Werk USA Breaks Ground on Manufacturing Facility in Gaston County

CHARLOTTE, N.C. (June 18, 2024) – HEYCO-Werk USA celebrated the start of construction of their new US manufacturing facility with...
EDIFICE Construction Ranks as a TOP General Contractor in Charleston Area

EDIFICE Construction Ranks as a TOP General Contractor in Charleston Area

We are thrilled to announce that EDIFICE Construction has achieved a remarkable milestone by securing the #8 spot in the...
Continental Tire Unveils Expanded Americas HQ in Lancaster County

Continental Tire Unveils Expanded Americas HQ in Lancaster County

Continental Tire the Americas has significantly expanded its Lancaster County headquarters operations. The tire giant yesterday unveiled its new, 90,000-square-foot...