Metrolina Park | January 2017

Despite some weather activity early January, Building #1 is moving right along with the completion of steel erection and ongoing roofing activities. Electrical, Mechanical and Plumbing crews are all on site and roughing in. Exterior patching is complete and the building is ready for paint.
Building #2 slab is almost complete with 9 of the 12 slabs in place. The first set of panels were poured in place and ready to stand. The park continues to take shape as we have made great progress on site utilities and roads. Grading activities also continue at lots 3-6.

Share This

Quick Links

In the News


Simpsonville Municipal Complex Groundbreaking

Simpsonville Municipal Complex Groundbreaking

Simpsonville, S.C. — The City of Simpsonville broke ground on Thursday on its new municipal complex in a ceremony onsite....
German manufacturer, H-T-L perma USA LP, breaks ground on new US  Headquarters in Charlotte

German manufacturer, H-T-L perma USA LP, breaks ground on new US Headquarters in Charlotte

Company is expanding manufacturing operations and moving to a new campus in Steele Creek. CHARLOTTE, N.C. (February 21, 2023) –...
Celebrating our Partners in Cajun Style

Celebrating our Partners in Cajun Style

Edifice held its annual Mardi Gras-themed subcontractor soiree on Fat Tuesday, February 21, 2023 at Lenny Boy Brewing in honor...