Monthly Project Status:

Construction Highlights Last 30 Days

  • Air/Vapor Barrier Start
  • Setting All Air Handlers
  • Sheathing In Courtyard Area D
  • Sheathing Fly Loft
  • Curtainwall Frames In Areas C, D, A
  • Setting Glass In Curtainwalls/Storefronts
  • All Slab On Decks Are Poured
  • Slab On Grade Area A Complete
  • Fire Line Installed & Tested
  • House Area CMU 90% Complete
  • Roofing At A/B
Update for April 2014

Monthly Photo Highlights include:

• Area C Storefront & Glazing

Area C Storefront & Glazing

• CMU At Courtyard Area B
CMU At Courtyard Area B

• CMU Walls Around Stage
CMU Walls Around Stage

• Courtyard Sheathing Area D
Courtyard Sheathing Area D

• Curtainwall At Hanover St.
Curtainwall At Hanover St.

• Curtainwall At Lobby
Curtainwall At Lobby

• Aerial overview: April 3, 2014
DSC_0506

Visit our Ox Blue Site to play time lapse construction thorough March 2014:

http://oxblue.com/open/edifice/all

 