UNC Charlotte’s University Recreation Center | June 2018

During the month of June, construction at the UNC Charlotte University Recreation Center project has continued to move forward. Post-tensioned concrete slab work is near completion, with a final pour date tentatively scheduled for the second week in July. Structural steel work at the knuckle area has now resumed, and structural trusses at the Gym area will follow behind this work. Exterior framing, sheathing, interior framing, and overhead rough-in work continue at the east section of the building. Roofing work is tentatively scheduled to begin in July at the east section of the building.

Additionally, the boiler installation and electrical duct bank work continue at the RUP building.