Project Update: November 2013

Monthly Project Status:

Progress photos of this month’s construction milestones

Monthly Highlights include:

• The “bottle opener” photo, a significant feature on the building.
This feature is an open canopy that will enable the light cannon can shine through during performances.

• Starting the final area of footings area A.

• The catwalks are the last part of the steel in the house area and the progress with the rough in at Area C.

Area A Footings Ready To Pour

• Area A Footings Ready To Pour

Area C Building Rough In

• Area C Building Rough In

Bottle Opener

• Bottle Opener

Catwalks At Sound Deflectors

• Catwalks At Sound Deflectors

Catwalks In House Area

• Catwalks In House Area

aerial cape fear dec 5

• Aerial Photo | Early December

Visit our Ox Blue Site to play time lapse construction thorough March 2014:

http://oxblue.com/open/edifice/all

 

Share This

Quick Links

Stay on top industry news with edifice

EDIFICE Construction Ranks as a TOP General Contractor in Charleston Area

EDIFICE Construction Ranks as a TOP General Contractor in Charleston Area

We are thrilled to announce that EDIFICE Construction has achieved a remarkable milestone by securing the #8 spot in the...
Continental Tire Unveils Expanded Americas HQ in Lancaster County

Continental Tire Unveils Expanded Americas HQ in Lancaster County

Continental Tire the Americas has significantly expanded its Lancaster County headquarters operations. The tire giant yesterday unveiled its new, 90,000-square-foot...
Committee and Volunteers photo with Santa

Santa Comes to Edifice for Some Reindeer Games

Last Saturday, the families of Edifice kicked off the holiday season with the Annual Breakfast with Santa event at Marvin...