Project Update: November 2013

Monthly Project Status:

Progress photos of this month’s construction milestones

Monthly Highlights include:

• The “bottle opener” photo, a significant feature on the building.
This feature is an open canopy that will enable the light cannon can shine through during performances.

• Starting the final area of footings area A.

• The catwalks are the last part of the steel in the house area and the progress with the rough in at Area C.

Area A Footings Ready To Pour

• Area A Footings Ready To Pour

Area C Building Rough In

• Area C Building Rough In

Bottle Opener

• Bottle Opener

Catwalks At Sound Deflectors

• Catwalks At Sound Deflectors

Catwalks In House Area

• Catwalks In House Area

aerial cape fear dec 5

• Aerial Photo | Early December

Visit our Ox Blue Site to play time lapse construction thorough March 2014:

http://oxblue.com/open/edifice/all

 

Share This

Quick Links

In the News


Live Feed: CMPD Central Division Facility

Live Feed: CMPD Central Division Facility

Follow along with the construction progress, via recent snapshot or a time-lapse, at Charlotte-Mecklenburg Police Department’s new Central Division Facility.
Huber_Technology_groundbreaking

Wastewater equipment manufacturer breaks ground on new HQ in Charlotte region

Look for Huber Technology Inc. to open its relocated headquarters in Lincoln County by early 2020 or potentially earlier —...
Edifice continues its support of Covenant Day and the ContainIt Project

Edifice continues its support of Covenant Day and the ContainIt Project

Edifice continues its support of Covenant Day as a key sponsor of their annual Sustainability Sporting Clay Shoot benefiting the ContainIt...