[pl_blockquote cite= “Look Ahead for Next 30 days — Posted: June 17, 2015”]
- Punch List Complete Building
- Start Fire Alarm Commissioning
- Install Curtains In House
- Performance Lighting/Sound Completion
- Complete all above ceiling inspections
- Final Inspections With City/County
- Owner Consultant Reviews
- Owner Training
[/pl_blockquote]