Project Update: June 2014

Construction Highlights Last 30 Days:
Area C

  • Brick Veneer (95% complete)
  • Storefront on West Elevation (65% complete)
  • Insulating Precast Panels (95% complete)

Area D

  • Structural Steel For First Floor Seating
  • Plenum Slab
  • First Floor Seating Area Concrete (80% complete)
  • Masonry At House To Roof  South
  • Courtyard Wall Sheathing
  • Stair F Framing / Sheathing
  • Curtainwall/Glazing In Lobby (80% complete)
  • Close Ramp to House
  • Metal Panels on Fly Loft (5% complete)
  • Spray Insulation on Precast Panels
  • Fly Loft Roofing

Area A

  • Exterior Wall Framing/Sheathing Courtyard
  • Air Barrier on Courtyard Wall
  • Exterior Wall Framing at South
  • Exterior Wall Sheathing at South
  • Interior Wall Framing  (85% complete)
  • Sprinkler Overhead Install (95% complete)
  • Curtainwall at South Elevation (85% complete)

Area B

  • Slab On Grade (85% complete)
  • Masonry (85% complete)
  • Roofing (50% complete)
  • Plumbing Underground Rough In (50% complete)
  • Brick Veneer (50% complete)

Monthly Photo Highlights include:

  • Progression on the House

House

  • North Elevation Masonry

North-Elevation-Work_1365x1024

  • Courtyard Masonry

Courtyard-Brick_1365x1024

  • South Exterior Storefront

Storefront-At-South-Exterior_1365x1024

  • Curtainwall in Lobby

Lobby-Curtainwall_1365x1024

  • June Aerial

DSC_0684

Share This

Quick Links

In the News


Play Button The Square at South End_January 2019

The Square at South End_January 2019

The Square at South End is officially underway! This initial drone video of job site progress shows the first concrete...
All the best to Max Venuti

All the best to Max Venuti

Edifice would like to formally thank Max Venuti for his dedication and service to our team during the past 14...
20th Annual Soup on Sunday

20th Annual Soup on Sunday

Join us on Sunday as we sponsor Hospice & Palliative Care Charlotte Region’s 20th ANNUAL SOUP ON SUNDAY. Hosted by the...