Project Update: June 2014

Construction Highlights Last 30 Days:
Area C

  • Brick Veneer (95% complete)
  • Storefront on West Elevation (65% complete)
  • Insulating Precast Panels (95% complete)

Area D

  • Structural Steel For First Floor Seating
  • Plenum Slab
  • First Floor Seating Area Concrete (80% complete)
  • Masonry At House To Roof  South
  • Courtyard Wall Sheathing
  • Stair F Framing / Sheathing
  • Curtainwall/Glazing In Lobby (80% complete)
  • Close Ramp to House
  • Metal Panels on Fly Loft (5% complete)
  • Spray Insulation on Precast Panels
  • Fly Loft Roofing

Area A

  • Exterior Wall Framing/Sheathing Courtyard
  • Air Barrier on Courtyard Wall
  • Exterior Wall Framing at South
  • Exterior Wall Sheathing at South
  • Interior Wall Framing  (85% complete)
  • Sprinkler Overhead Install (95% complete)
  • Curtainwall at South Elevation (85% complete)

Area B

  • Slab On Grade (85% complete)
  • Masonry (85% complete)
  • Roofing (50% complete)
  • Plumbing Underground Rough In (50% complete)
  • Brick Veneer (50% complete)

Monthly Photo Highlights include:

  • Progression on the House

House

  • North Elevation Masonry

North-Elevation-Work_1365x1024

  • Courtyard Masonry

Courtyard-Brick_1365x1024

  • South Exterior Storefront

Storefront-At-South-Exterior_1365x1024

  • Curtainwall in Lobby

Lobby-Curtainwall_1365x1024

  • June Aerial

DSC_0684

Share This

Quick Links

In the News


AmericanLegionMemorialStadium

Groundbreaking Ceremony | American Legion Memorial Stadium

As this exciting new project gets underway, our construction team of Edifice, Barton Malow, NJR Construction and Lil Associates II,...
Chris Socha Board of Pat's Place

Chris Socha named to the Board of Directors of Pat’s Place Child Advocacy Center

Edifice would like to congratulate Chris Socha for being named to the board of directors of Pat’s Place Child Advocacy...