Construction Highlights Last 30 Days:

Area C

  • Brick Veneer (95% complete)
  • Storefront on West Elevation (65% complete)
  • Insulating Precast Panels (95% complete)

Area D

  • Structural Steel For First Floor Seating
  • Plenum Slab
  • First Floor Seating Area Concrete (80% complete)
  • Masonry At House To Roof  South
  • Courtyard Wall Sheathing
  • Stair F Framing / Sheathing
  • Curtainwall/Glazing In Lobby (80% complete)
  • Close Ramp to House
  • Metal Panels on Fly Loft (5% complete)
  • Spray Insulation on Precast Panels
  • Fly Loft Roofing

Area A

  • Exterior Wall Framing/Sheathing Courtyard
  • Air Barrier on Courtyard Wall
  • Exterior Wall Framing at South
  • Exterior Wall Sheathing at South
  • Interior Wall Framing  (85% complete)
  • Sprinkler Overhead Install (95% complete)
  • Curtainwall at South Elevation (85% complete)

Area B

  • Slab On Grade (85% complete)
  • Masonry (85% complete)
  • Roofing (50% complete)
  • Plumbing Underground Rough In (50% complete)
  • Brick Veneer (50% complete)
Update for June 2014

 Monthly Photo Highlights include:

  • Progression on the House

House

  • North Elevation Masonry

North-Elevation-Work_1365x1024

  • Courtyard Masonry

Courtyard-Brick_1365x1024

  • South Exterior Storefront

Storefront-At-South-Exterior_1365x1024

  • Curtainwall in Lobby

Lobby-Curtainwall_1365x1024

  • June Aerial

DSC_0684