Project Update: March 2015

A list of the project’s milestones and action items that have been completed within the last 30 days for the CFCC Humanities and Fine Arts Center project.

Construction Highlights Last 30 Days: CFCC

[pl_blockquote cite= “Update for March 2015”]

  • Above Ceiling Inspections A/B/C Completed
  • Exterior Concrete Sidewalks at North Side
  • Exterior Concrete at South Plaza
  • Exterior Sign Wall Precast Panels
  • Ceiling Grid in High Lobby
  • Extension of Elevator Shaft 1/2 & Roofing
  • Flooring in Areas A/B
  • Painting in House Area
  • Fabric Walls in House Area
  • Start Heat in Area C
  • Plumbing Fixtures A/B/C
  • Stainless Steel Tops in Area A
  • Wood Doors in A/B

[/pl_blockquote]Monthly Photo Highlights Include:

Click on the photos below to view the full photo. [hover category=”CFCCBlog_March”]

Share This

Quick Links

In the News


Live Feed: EC Specialty School

Live Feed: EC Specialty School

Follow along as construction progresses at CMS’ new EC Specialty School. You can view a recent snapshot of the site,...
Metrolina_Park

Metrolina Park Wins Heavy Hitters Award for Warehouse Development

Metrolina Park was honored with a Heavy Hitters Award for warehouse development. These awards recognize the best in commercial real...
The Pastors Masters Heads to Old North State Club for 2018

The Pastors Masters Heads to Old North State Club for 2018

After many years of hosting the Pastors Masters Golf Tournament at the beautiful Club at Longview, Edifice, Inc. decided it...