The RailYard | May 2018

The video footage is from May 24, 2018 at the RailYard project in Charlotte, NC. The North and South Towers are under construction, the tower on the top left at the beginning of the video is the North Tower. The steel is completely erected and the elevated concrete slabs placed. The exterior framing and sheathing is being installed. Scaffolding has been erected on two sides of the building in order to complete the elevated work at the exterior of the building. The green tarp is temporarily installed at the 8th Floor to contain the ongoing spray fireproofing of the steel. The steel erection is ongoing on the South Tower. The crane is set-up in the future courtyard of the project. After the South Tower steel is erected, the connector between the towers and the precast parking deck behind the building will be erected.