The Refinery | May 2018

This past month’s construction activities on The Refinery is pretty impressive. The structural steel erection is complete as well as the foundation walls and waterproofing of the perimeter walls at the parking deck. While we continue with the decking and detailing, under slab utilities within the building are underway.

Share This

Quick Links