University Recreation Center | November 2017

During the month of November, work at the UNC Charlotte University Recreation Center project continues to progress with the concrete trade contractor continuing their installation of concrete foundations and retaining walls at the first floor level of the building. They have also started working their way up the hill to complete a portion of the 2nd-floor foundations and retaining walls. Under-slab utility work at the first floor is scheduled to begin mid-December. Site work trade contractor is continuing with the installation of underground site storm and sanitary sewer systems.

 