UNC Charlotte’s University Recreation Center | May 2018

During the month of May, construction at the UNC Charlotte University Recreation Center Project has progressed very well. A substantial amount of work was completed on the post-tensioned concrete slabs, which are now tentatively scheduled to be completed in July. Structural steel work is continuing at the east section of the building and will follow behind the post tensioned concrete slab work at the west section after it is completed. Fireproofing, exterior framing, interior framing, and overhead rough-in work has begun at the east section of the building.

Share This

Quick Links