Project Update: October 2014
Construction Highlights Last 30 Days:
- Completed Roofing
- Veneer on Building Completed
- Utility Work Completed
- Walls Hung and Finished Area A/B Level 02/03
- Walls Hung and Finished Area C Level 01
- Wall Framing Complete Area C Level 02 & Area A/B Level 01
- Upper House Framing & Painting Complete
- Painting Started on Stage & Back of House Areas
- Metal Panels on North Side of House 50%
- Metal Panels on Stair F 100%
- Sheathing on Lobby Overhang 100%
- Permanent Power On