Project Update: October 2014

Construction Highlights Last 30 Days:

  • Completed Roofing
  • Veneer on Building Completed
  • Utility Work Completed
  • Walls Hung and Finished Area A/B Level 02/03
  • Walls Hung and Finished Area C Level 01
  • Wall Framing Complete Area C Level 02 & Area A/B Level 01
  • Upper House Framing & Painting Complete
  • Painting Started on Stage & Back of House Areas
  • Metal Panels on North Side of House 50%
  • Metal Panels on Stair F 100%
  • Sheathing on Lobby Overhang 100%
  • Permanent Power On

Monthly Photo Highlights Include:

West Exterior Progress West-Exterior-Progress

Progress on Stair F & Lobby Stair-F-&-Lobby-Progress

Monumental Stair in Lobby Monumental-Stair-In-Lobby

Finishing Walls in Areas A & B Finishing-Walls-In-Area-A-&-B

Curb Installation on Hanover Curb-Install-On-Hanover

Project Aerial: October 15, 2014
DSC_0569

Share This

Quick Links

Stay on top industry news with edifice

Committee and Volunteers photo with Santa

Santa Comes to Edifice for Some Reindeer Games

Last Saturday, the families of Edifice kicked off the holiday season with the Annual Breakfast with Santa event at Marvin...
People in dirndl and lederhosen dance with a stilt walker at a carnival at dusk. There is a ferris wheel in the background.

Prost to the 2023 Fall Party | Oktoberfeier

There’s no better way to spend the first day of fall – with good food and fun, surrounded by family...
2023 North Carolina Mid-Market Fast 40 Logo

Business North Carolina Announced Mid-Market Fast 40

EDIFICE ranked #5  Forty fast-growing North Carolina middle-market companies were celebrated for their entrepreneurial spirit and strong revenue growth this...