Christ Covenant Church | November 2015

Project Update:Click Here to view the live construction cam feed! Christ Covenant Church

Despite the record rainfall amounts on the Christ Covenant site, we managed to get several key things in place, including the elevator pit, surrounding walls, and the lower level slab. We also completed backfilling on the north side of the lower level last week.

The large detention ponds adjacent to the Community Life Center have been under construction. We have completed 90% of the storm pipe and the outflow structures. Currently, demolition of the adjacent road is underway, which will become part of the larger detention pond. In addition to the work on the ponds, we plan to pave several miscellaneous parking and drive isles this week.

Christ Covenant Church Monthly Photo Highlights:

Click on the photos below to view the full photo.

[hover_pack img=”https://edificeinc.com/wp-content/uploads/2015/11/Image-11-17-15-8.57.39-AM.jpg” link=”https://edificeinc.com/wp-content/uploads/2015/11/Image-11-17-15-8.57.39-AM.jpg” width=”338″ height=”292″ opacity=”70″]

[hover_pack img=”https://edificeinc.com/wp-content/uploads/2015/11/Image-10-23-15-1.12.15-PM.jpg” link=”https://edificeinc.com/wp-content/uploads/2015/11/Image-10-23-15-1.12.15-PM.jpg” width=”338″ height=”292″ opacity=”70″]

[hover_pack img=”https://edificeinc.com/wp-content/uploads/2015/11/Image-10-22-15-1.48.42-PM.jpg” link=”https://edificeinc.com/wp-content/uploads/2015/11/Image-10-22-15-1.48.42-PM.jpg” width=”225″ height=”300″ opacity=”70″]

[hover_pack img=”https://edificeinc.com/wp-content/uploads/2015/11/Image-10-30-15-5.33.56-PM.jpg” link=”https://edificeinc.com/wp-content/uploads/2015/11/Image-10-30-15-5.33.56-PM.jpg” width=”225″ height=”300″ opacity=”70″]

[hover_pack img=”https://edificeinc.com/wp-content/uploads/2015/11/Image-11-6-15-10.43.26-AM.jpg” link=”https://edificeinc.com/wp-content/uploads/2015/11/Image-11-6-15-10.43.26-AM.jpg” width=”225″ height=”300″ opacity=”70″]

[hover_pack img=”https://edificeinc.com/wp-content/uploads/2015/11/Image-10-27-15-8.45.50-AM.jpg” link=”https://edificeinc.com/wp-content/uploads/2015/11/Image-10-27-15-8.45.50-AM.jpg” width=”338″ height=”225″ opacity=”70″]

[hover_pack img=”https://edificeinc.com/wp-content/uploads/2015/11/Image-11-17-15-9.16.02-AM.jpg” link=”https://edificeinc.com/wp-content/uploads/2015/11/Image-11-17-15-9.16.02-AM.jpg” width=”338″ height=”225″ opacity=”70″]

[hover_pack img=”https://edificeinc.com/wp-content/uploads/2015/11/Image-11-12-15-11.21.43-AM.jpg” link=”https://edificeinc.com/wp-content/uploads/2015/11/Image-11-12-15-11.21.43-AM.jpg” width=”225″ height=”300″ opacity=”70″]

[hover_pack img=”https://edificeinc.com/wp-content/uploads/2015/11/Image-11-18-15-9.14.35-AM.jpg” link=”https://edificeinc.com/wp-content/uploads/2015/11/Image-11-18-15-9.14.35-AM.jpg” width=”225″ height=”300″ opacity=”70″]

[hover_pack img=”https://edificeinc.com/wp-content/uploads/2015/11/Image-11-18-15-8.50.41-AM.jpg” link=”https://edificeinc.com/wp-content/uploads/2015/11/Image-11-18-15-8.50.41-AM.jpg” width=”225″ height=”300″ opacity=”70″]

Share This

Quick Links

In the News


Dorchester County Economic Development Commences Construction with a Groundbreaking Ceremony for New Commerce Center in Summerville

Dorchester County Economic Development Commences Construction with a Groundbreaking Ceremony for New Commerce Center in Summerville

SUMMERVILLE, S.C. (November 16, 2022) – Dorchester County Economic Development held a groundbreaking ceremony earlier this week to commence construction...
City of Statesville breaks ground on the new Fire Station

City of Statesville breaks ground on the new Fire Station

(Statesville, NC) City leaders and fire department personnel broke ground for the new Fire Station One on Wednesday, November 30...
Prost to our 2022 Fall Party | Oktoberfeier!

Prost to our 2022 Fall Party | Oktoberfeier!

After a 2 year break (thanks COVID) Oktoberfeier returned. Just as the seasons started to change and with fall in...