Christ Covenant Church | October 2015

Project Update:Click Here to view the live construction cam feed! Christ Covenant Church

In between the rain events this past month at the Christ Covenant Church site, we have worked primarily on the footings and the large foundation retaining walls that form the Lower Level of the Community Life Center. There is about one week of work left on these foundation walls before they are completed. The week of October 26th, we will begin laying block for the elevator and stair tower. Later that same week we will also be pouring the lower level slab.

The retaining walls have been waterproofed and are currently being backfilled. After this task is completed, we will continue to work on the footings for the upper level. The upper slab (Level 1) will be poured sometime in mid-November just prior to the steel erection, which is scheduled for Nov. 23rd.

Christ Covenant Church Monthly Photo Highlights:

Click on the photos below to view the full photo.

[hover_pack img=”https://edificeinc.com/wp-content/uploads/2015/10/Image-9-16-15-3.20.28-PM.jpg” link=”https://edificeinc.com/wp-content/uploads/2015/10/Image-9-16-15-3.20.28-PM.jpg” width=”180″ height=”250″ opacity=”70″]

[hover_pack img=”https://edificeinc.com/wp-content/uploads/2015/10/Image-9-18-15-1.09.15-PM.jpg” link=”https://edificeinc.com/wp-content/uploads/2015/10/Image-9-18-15-1.09.15-PM.jpg” width=”180″ height=”250″ opacity=”70″]

[hover_pack img=”https://edificeinc.com/wp-content/uploads/2015/10/Image-9-18-15-11.31.10-AM.jpg” link=”https://edificeinc.com/wp-content/uploads/2015/10/Image-9-18-15-11.31.10-AM.jpg” width=”299″ height=”250″ opacity=”70″]

[hover_pack img=”https://edificeinc.com/wp-content/uploads/2015/10/Image-9-18-15-3.54.26-PM.jpg” link=”https://edificeinc.com/wp-content/uploads/2015/10/Image-9-18-15-3.54.26-PM.jpg” width=”243″ height=”225″ opacity=”70″]

[hover_pack img=”https://edificeinc.com/wp-content/uploads/2015/10/Image-9-21-15-8.32.13-AM.jpg” link=”https://edificeinc.com/wp-content/uploads/2015/10/Image-9-21-15-8.32.13-AM.jpg” width=”243″ height=”225″ opacity=”70″]

[hover_pack img=”https://edificeinc.com/wp-content/uploads/2015/10/Image-9-21-15-8.33.42-AM.jpg” link=”https://edificeinc.com/wp-content/uploads/2015/10/Image-9-21-15-8.33.42-AM.jpg” width=”173″ height=”225″ opacity=”70″]

[hover_pack img=”https://edificeinc.com/wp-content/uploads/2015/10/Image-10-6-15-2.55.43-PM.jpg” link=”https://edificeinc.com/wp-content/uploads/2015/10/Image-10-6-15-2.55.43-PM.jpg” width=”243″ height=”225″ opacity=”70″]

[hover_pack img=”https://edificeinc.com/wp-content/uploads/2015/10/IMG_4662.jpg” link=”https://edificeinc.com/wp-content/uploads/2015/10/IMG_4662.jpg” width=”173″ height=”225″ opacity=”70″]

[hover_pack img=”https://edificeinc.com/wp-content/uploads/2015/10/IMG_4665.jpg” link=”https://edificeinc.com/wp-content/uploads/2015/10/IMG_4665.jpg” width=”243″ height=”225″ opacity=”70″]

Share This

Quick Links

In the News


Live Feed: CMPD Central Division Facility

Live Feed: CMPD Central Division Facility

Follow along with the construction progress, via recent snapshot or a time-lapse, at Charlotte-Mecklenburg Police Department’s new Central Division Facility.
Huber_Technology_groundbreaking

Wastewater equipment manufacturer breaks ground on new HQ in Charlotte region

Look for Huber Technology Inc. to open its relocated headquarters in Lincoln County by early 2020 or potentially earlier —...
Edifice continues its support of Covenant Day and the ContainIt Project

Edifice continues its support of Covenant Day and the ContainIt Project

Edifice continues its support of Covenant Day as a key sponsor of their annual Sustainability Sporting Clay Shoot benefiting the ContainIt...