Metrolina Park | December 2016
Upon the completion of the slab for Building #1, Seretta immediately began forming the tilt up panels on site. The architectural details of the panels involve intricate reveals and interesting angles that in the end will create a unique and beautiful building. Also in the video you will see the progress of the building pad #2. The footings are completed and work on the perimeter foundations that will support the precast has started. The pad for Building #3 was prepped and is currently be used for parking and material lay down. Hoopaugh Grading, LLC continues the earthwork for Buildings #4 & #5.