Monthly Project Status:

Construction Highlights Last 30 Days

Work Completed this month:

  • Parking Lot Base Installation
  • Pond Clearing
  • Installation of New Pond Structure & Pipe
  • Tilt-up Concrete Panel Installation
  • Steel Framing & Roof Decking
  • First Beam Installation and Start Tie into Existing Building
  • Start Storefront Framing & Glass at the Exterior Building
  • Interior Electrical Demolition and Relocation of Panel
  • Rough in of New Sprinkler System at Existing Building
  • Prep for Office Build-Out
Update for April 2014

Monthly Photo Highlights include:

• Concrete tilt wall panels formed and poured
Poured-concrete-panels_1024x673

Concrete-Tilt-walls-formed-&-poured_1224x1632

• Setting concrete wall panels

Setting-1st-panel-1024x671    Concrete-panels-setting-576x768

      

• Steel Framing and Roof Decking

Roof-Decking_1024x768

Steel-Framing_480x640    Steel-Framing-of-Expansion_1024x768

• Pond clearing

pond-clearing-640x640

 

• Pond dressing

pond-dressing-640x480

 

• Statesville Road Elevation

Statesville-Rd-elevation-853x640

 

• Storefront frames and glass

Storefront-frames-&-glass-960x720

 

• Forming new dock pit

Forming-new-dock-pit-960x720