Project Update: April 2014
Monthly Project Status:
[pl_blockquote cite= “Update for April 2014”]
Construction Highlights Last 30 Days
Work Completed this month:
- Parking Lot Base Installation
- Pond Clearing
- Installation of New Pond Structure & Pipe
- Tilt-up Concrete Panel Installation
- Steel Framing & Roof Decking
- First Beam Installation and Start Tie into Existing Building
- Start Storefront Framing & Glass at the Exterior Building
- Interior Electrical Demolition and Relocation of Panel
- Rough in of New Sprinkler System at Existing Building
- Prep for Office Build-Out
[/pl_blockquote]
Monthly Photo Highlights include:
• Concrete tilt wall panels formed and poured
• Setting concrete wall panels
• Steel Framing and Roof Decking
• Pond clearing
• Pond dressing
• Statesville Road Elevation
• Storefront frames and glass
• Forming new dock pit