Project Update: April 2015

A list of the project’s milestones and action items that have been completed within the last 30 days for the CFCC Humanities and Fine Arts Center project.

Construction Highlights Last 30 Days: CFCC

[pl_blockquote cite= “Update for April 2015”]

  • Installed Elevators 1/2
  • Started Flooring in Area C
  • Installed Wood Doors in Area C
  • Started House Seating Install
  • Started Wood Flooring Install
  • Finished Landscaping & Irrigation
  • Above Ceiling Inspections in Area D
  • Ceiling Grid in Prefunction Area
  • Partition Installed in Prefunction Area
  • Finishing Lobby Walls & Soffits
  • Proscenium Fire Curtain Installed
  • Stage Rigging & Curtain Track Installed

[/pl_blockquote]Monthly Photo Highlights Include:

Click on the photos below to view the full photo. [hover category=”CFCCBlog_April”] 

Share This

Quick Links

In the News


Live Feed: CMPD Central Division Facility

Live Feed: CMPD Central Division Facility

Follow along with the construction progress, via recent snapshot or a time-lapse, at Charlotte-Mecklenburg Police Department’s new Central Division Facility.
Huber_Technology_groundbreaking

Wastewater equipment manufacturer breaks ground on new HQ in Charlotte region

Look for Huber Technology Inc. to open its relocated headquarters in Lincoln County by early 2020 or potentially earlier —...
Edifice continues its support of Covenant Day and the ContainIt Project

Edifice continues its support of Covenant Day and the ContainIt Project

Edifice continues its support of Covenant Day as a key sponsor of their annual Sustainability Sporting Clay Shoot benefiting the ContainIt...