Project Update: April 2015

A list of the project’s milestones and action items that have been completed within the last 30 days for the CFCC Humanities and Fine Arts Center project.

Construction Highlights Last 30 Days: CFCC

[pl_blockquote cite= “Update for April 2015”]

  • Installed Elevators 1/2
  • Started Flooring in Area C
  • Installed Wood Doors in Area C
  • Started House Seating Install
  • Started Wood Flooring Install
  • Finished Landscaping & Irrigation
  • Above Ceiling Inspections in Area D
  • Ceiling Grid in Prefunction Area
  • Partition Installed in Prefunction Area
  • Finishing Lobby Walls & Soffits
  • Proscenium Fire Curtain Installed
  • Stage Rigging & Curtain Track Installed

[/pl_blockquote]Monthly Photo Highlights Include:

Click on the photos below to view the full photo. [hover category=”CFCCBlog_April”] 

Share This

Quick Links

In the News


Local financial-services firm to build new Cornelius HQ as part of $22.5M investment

Local financial-services firm to build new Cornelius HQ as part of $22.5M investment

Financial Independence Group LLC is moving its headquarters to a new site in Cornelius as part of a $22.5 million...
Former EDIFICE CEO Eric Laster on what’s ahead for one of Charlotte’s biggest contractors

Former EDIFICE CEO Eric Laster on what’s ahead for one of Charlotte’s biggest contractors

Eric Laster spent the past three decades turning Edifice into a general-contracting powerhouse, first in Charlotte and then across the Southeast....
EDIFICE Supports First Tee Charleston with Recent Donation

EDIFICE Supports First Tee Charleston with Recent Donation

We are excited to announce a recent $10,000 donation to First Tee Charleston. The pledge supports First Tee’s Building Futures...