Project Update: August 2014
Construction Highlights Last 30 Days:
- Completed Glazing the Storefront West Elevation
- Completed Masonry on North Elevation
- Closed Masonry Access
- Completed Sheathing on the North Elevation
- Stair F Framing & Sheathing Completed
- Completed the Framing & Rough In for Level 02 of the Balcony Ceiling
- Proscenium Wall Framing Completed
- Metal Panels Installed at Fly Loft
- Slab on Grade Completed at Area B
Monthly Photo Highlights Include:
Framing Balcony Railing
Progress on the West Wall
Metal Panels on the Fly Loft
Underground in the Courtyard
Roofing at Areas B & C
Prepping Final Slab on Grade
Project Aerial: August 14, 2014
Visit our Ox Blue Site to play time lapse construction thorough March 2014: http://oxblue.com/open/edifice/all