Construction Highlights Last 30 Days:

  • Completed Glazing the Storefront West Elevation
  • Completed Masonry on North Elevation
  • Closed Masonry Access
  • Completed Sheathing on the North Elevation
  • Stair F Framing & Sheathing Completed
  • Completed the Framing & Rough In for Level 02 of the Balcony Ceiling
  • Proscenium Wall Framing Completed
  • Metal Panels Installed at Fly Loft
  • Slab on Grade Completed at Area B
Update for August 2014

Monthly Photo Highlights Include:

Framing Balcony Railing Balcony-Framing-Railing1024x768
Progress on the West Wall     West-Wall-Progress.1024x716
Metal Panels on the Fly Loft  Metal-Panels-On-Fly-Loft.1024x768
Underground in the Courtyard     Underground In Courtyard
Roofing at Areas B & C Roofing-At-Area-B-C.1024x768
Prepping Final Slab on Grade   Prepping Final Slab on Grade
Project Aerial: August 14, 2014 DSC_0072.1024x777

Visit our Ox Blue Site to play time lapse construction thorough March 2014: http://oxblue.com/open/edifice/all

Share →