Project Update: March 2014

Monthly Project Status:

Construction Highlights Last 30 Days

  • Roofing On The Lobby Area
  • Completion Of Precast Panels
  • Start Of Curtainwall/Storefront Systems
  • Set Cooling Tower and Chiller
  • Completion Of Performance Stage Slab
  • Start Masonry Around Stage and house Area
  • Poured all Slab On Decks In Area B

Monthly Photo Highlights include:

• Cooling Tower & Precast On West Elevation

Cooling Tower & Precast On West Elevation

• Masonry Around Stage

Masonry Around Stage

• Pouring Balcony Seating Risers

Pouring Balcony Seating Risers

• Precast at South Side Of Building

Precast at South Side Of Building

• Precast Picture Frame

Precast Picture Frame

• Aerial View: March 2, 2014

DSC_0497

Visit our Ox Blue Site to play time lapse construction thorough March 2014:

http://oxblue.com/open/edifice/all

 

Share This

Quick Links

In the News


Play Button Iredell Public Safety Complex | May 2018

Iredell Public Safety Complex | May 2018

Things are moving right along at the Iredell County Public Safety Project. The exterior facade is dried in enough to...
ENR_Southeast_Top_Contractors

Edifice moves up on ENR’s Top Southeast Contractors List

Edifice moved up nine places on the prestigious Southeast Top Contractor’s List.  Engineering-News Record (ENR) yearly ranks the largest general contractors, both...
Supporting Pat’s Place for the Children of Mecklenburg County

Supporting Pat’s Place for the Children of Mecklenburg County

We are pleased to begin a multi-year sponsorship with Pat’s Place Child Advocacy Center. Earlier this year we announced our...