Project Update: February 2014

Monthly Project Status:

Construction Highlights Last 30 Days

  • Precast Panel Start (Photo from Precast Ceremony)
  • Structural Steel Substantially Complete In All Areas
  • First Slab On Grade Pour In Area D
  • Slab On Decks Poured At Area A
  • Parapet Framing On Lobby Roof

[/pl_blockquote]

Monthly Photo Highlights include:

• Photo from Precast Ceremony

Photo from Precast Ceremony

• Formwork At Balcony Seats

Formwork At Balcony Seats

• Performing Slab Shoring

Performing Slab Shoring

• Precast At West Elevation

Precast At West Elevation

• Structural Steel Area A

Structural Steel Area A

• Underground Rough In Area A

Underground Rough In Area A

• Aerial: February 5, 2014

DSC_0348

 

Visit our Ox Blue Site to play time lapse construction thorough March 2014:

http://oxblue.com/open/edifice/all

Share This

Quick Links

In the News


Play Button The Square at South End | September 2020

The Square at South End | September 2020

The Square at South End continues to impress. The parking deck structure is complete and the site cleared around it...
St. Joseph College Seminary in Mount Holly named General Contractor Project of the Year

St. Joseph College Seminary in Mount Holly named General Contractor Project of the Year

The Associated Builders and Contractors of the Carolinas (ABCC) announced that the 2020 GC Project of the Year, presented by Adams...
Supporting the Salvation Army Angel Tree Project

Supporting the Salvation Army Angel Tree Project

EDIFICE employees once again stepped up to bring a little holiday cheer to our smallest neighbors in need. Employees pitched in...