Project Update: February 2014

Monthly Project Status:

Construction Highlights Last 30 Days

  • Precast Panel Start (Photo from Precast Ceremony)
  • Structural Steel Substantially Complete In All Areas
  • First Slab On Grade Pour In Area D
  • Slab On Decks Poured At Area A
  • Parapet Framing On Lobby Roof

[/pl_blockquote]

Monthly Photo Highlights include:

• Photo from Precast Ceremony

Photo from Precast Ceremony

• Formwork At Balcony Seats

Formwork At Balcony Seats

• Performing Slab Shoring

Performing Slab Shoring

• Precast At West Elevation

Precast At West Elevation

• Structural Steel Area A

Structural Steel Area A

• Underground Rough In Area A

Underground Rough In Area A

• Aerial: February 5, 2014

DSC_0348

 

Visit our Ox Blue Site to play time lapse construction thorough March 2014:

http://oxblue.com/open/edifice/all

Stay on top industry news with edifice

Pineville Town Hall and Library: Award-Winning Community Transformation

Pineville Town Hall and Library: Award-Winning Community Transformation

Have you ever wondered how a single construction project can transform an entire community? The Pineville Town Hall and Library...
Celebrating Eric Laster’s Legacy and Retirement

Celebrating Eric Laster’s Legacy and Retirement

On December 13, 2024, Edifice Construction gathered at the prestigious Quail Hollow Country Club in Charlotte, NC, to honor a...
Lil’ Tykes Christmas Party: A Grinchmas Celebration

Lil’ Tykes Christmas Party: A Grinchmas Celebration

On Saturday, December 7th, Edifice families gathered for our annual Lil’ Tykes Christmas Party at the Barn at Marvin Efird...