Project Update: July 2014
Construction Highlights Last 30 Days:
Area C
- Completed Glazing the Storefront West Elevation
- Close to Completing the MEPS Wall Rough In (95% complete)
- Acoustical Wall Installation (50% complete)
Area D
- Completed the Masonry on the North Elevation
- Completed the Courtyard Brick
- Poured the 1st Level Balcony Slab
- Erected the Scaffold for the House Ceiling Work
- Completed the Framing & Rough In for the Balcony Ceiling Level 02
- Masonry Access Closed (95% complete)
- Complete Sheathing on North Elevation (90% complete)
- Proscenium Wall Framing (90% complete)
- Stair F Framing & Sheathing (80% complete)
- Interior Wall Framing (80% complete)
- Lobby Canopy Framing (70% complete)
- Metal Panels at Fly Loft (60% complete)
- Balcony Ceiling Framing & Rough In Level 03 (50% complete)
- MEPS Overhead Rough In House Ceiling (35% complete)
- Framing Interior of House (25% complete)
- Concrete Steps (10% complete)
Area A
- Completed the Air Barrier
- Completed the Brick at Courtyard
- Storefront Glazing on South Side (95% complete)
- Interior Framing (90% complete)
- Storefront in Courtyard (85% complete)
- MEPS Rough In Walls (75% complete)
Area B
- Completed Elevator #4 Masonry
- Completed the Cooling Tower CMU
- CMU Masonry Interior (90% complete)
- Slab On Grade (70% complete)
- Brick at Stair B (50% complete)
- CMU West Elevation (35% complete)