Project Update: July 2014

CFCC_AllAreasConstruction Highlights Last 30 Days:

Area C

  • Completed Glazing the Storefront West Elevation
  • Close to Completing the MEPS Wall Rough In (95% complete)
  • Acoustical Wall Installation (50% complete)

Area D

  • Completed the Masonry on the North Elevation
  • Completed the Courtyard Brick
  • Poured the 1st Level Balcony Slab
  • Erected the Scaffold for the House Ceiling Work
  • Completed the Framing & Rough In for the Balcony Ceiling Level 02
  • Masonry Access Closed (95% complete)
  • Complete Sheathing on North Elevation (90% complete)
  • Proscenium Wall Framing (90% complete)
  • Stair F Framing & Sheathing (80% complete)
  • Interior Wall Framing (80% complete)
  • Lobby Canopy Framing (70% complete)
  • Metal Panels at Fly Loft (60% complete)
  • Balcony Ceiling Framing & Rough In Level 03 (50% complete)
  • MEPS Overhead Rough In House Ceiling (35% complete)
  • Framing Interior of House (25% complete)
  • Concrete Steps (10% complete)

Area A

  • Completed the Air Barrier
  • Completed the Brick at Courtyard
  • Storefront Glazing on South Side (95% complete)
  • Interior Framing  (90% complete)
  • Storefront in Courtyard (85% complete)
  • MEPS Rough In Walls (75% complete)

Area B

  • Completed Elevator #4 Masonry
  • Completed the Cooling Tower CMU
  • CMU Masonry Interior (90% complete)
  • Slab On Grade (70% complete)
  • Brick at Stair B (50% complete)
  • CMU West Elevation (35% complete)

Monthly Photo Highlights Include:
ScaffoldingInHouse.1024x768

West-Elevation-Progress_1024x768

Proscenium-Wall-Progress_1024x768

Lobby-Exterior-With-Overhand-Framing_1024x768

Courtyard-Brick-&-Storefront_1024x768

South-Exterior-Progress_1024x768

Aerial_7.15.14_1024x683

Share This

Quick Links

In the News


Live Feed: CMPD Central Division Facility

Live Feed: CMPD Central Division Facility

Follow along with the construction progress, via recent snapshot or a time-lapse, at Charlotte-Mecklenburg Police Department’s new Central Division Facility.
Huber_Technology_groundbreaking

Wastewater equipment manufacturer breaks ground on new HQ in Charlotte region

Look for Huber Technology Inc. to open its relocated headquarters in Lincoln County by early 2020 or potentially earlier —...
Edifice continues its support of Covenant Day and the ContainIt Project

Edifice continues its support of Covenant Day and the ContainIt Project

Edifice continues its support of Covenant Day as a key sponsor of their annual Sustainability Sporting Clay Shoot benefiting the ContainIt...