Project Update: May 2014

Monthly Project Status:

Construction Highlights Last 30 Days

Work Completed this month:

  • Completed pond
  • Completed Demolition of exterior wall and tie in to new building
  • Installation of TPO Roof
  • Framing & Drywall Installation in office
  • Prime Exterior and Interior walls
  • Rough in of all MEP
  • Install Sprinkler Pipe
  • Concrete Pavement and ramp at Docks
  • Misc Concrete (Dolly Pads and Curbs)
  • Installation dock equipment

Monthly Photo Highlights include:

  • Completion of Pond

Completion-of-Pond_853x640

  • Demolition of Exterior Wall and Tie-In to New Structure

Demolition-of-exterior-wall-and-tie-in-to-new-structure_853x640

  • Completion of Demolition of Exterior Wall

Exterior-Wall-Demolition-Complete_853x640

  • Office Framing and Drywall Installation

Office-Framing-&-Drywall-Installation_640x640

  • Pavement Installation at Docks

Pavement-Installation-at-Docks_480x640

  • Curb and Gutter Installation

Curb-&-gutter640x640

  • Dock Equipment Installation

 

Dock-Equipment-Installationz_480x640

Share This

Quick Links

In the News


Play Button CrossRidge Building One | February 2021

CrossRidge Building One | February 2021

The CrossRidge Office Building One is moving right along! This month’s video features finalizing the slab finish after a morning...
EDIFICE Promotes Gaius Carter to Project Executive

EDIFICE Promotes Gaius Carter to Project Executive

EDIFICE is pleased to announce that Gaius Carter has been promoted to Project Executive focusing on the manufacturing sector. Gaius has...
The John Crosland School Takes Learning in a New Direction

The John Crosland School Takes Learning in a New Direction

EDIFICE, along with a group of great partners, helped bring the John Crosland School’s outdoor pavilion to life. ¬†Watch how...