Project Update: May 2014

Monthly Project Status:

Construction Highlights Last 30 Days

Work Completed this month:

  • Completed pond
  • Completed Demolition of exterior wall and tie in to new building
  • Installation of TPO Roof
  • Framing & Drywall Installation in office
  • Prime Exterior and Interior walls
  • Rough in of all MEP
  • Install Sprinkler Pipe
  • Concrete Pavement and ramp at Docks
  • Misc Concrete (Dolly Pads and Curbs)
  • Installation dock equipment

Monthly Photo Highlights include:

  • Completion of Pond

Completion-of-Pond_853x640

  • Demolition of Exterior Wall and Tie-In to New Structure

Demolition-of-exterior-wall-and-tie-in-to-new-structure_853x640

  • Completion of Demolition of Exterior Wall

Exterior-Wall-Demolition-Complete_853x640

  • Office Framing and Drywall Installation

Office-Framing-&-Drywall-Installation_640x640

  • Pavement Installation at Docks

Pavement-Installation-at-Docks_480x640

  • Curb and Gutter Installation

Curb-&-gutter640x640

  • Dock Equipment Installation

 

Dock-Equipment-Installationz_480x640

Share This

Quick Links

In the News


Groundbreaking underway for speculative Class-A office building in CrossRidge Center

Groundbreaking underway for speculative Class-A office building in CrossRidge Center

190-acre campus adding the 120,000 s.f. building to its development Indian Land, S.C., August 18, 2020 — CrossRidge Center continues...
Charleston Team

Edifice Expands to Charleston

Edifice, the regional general contractor headquartered in Charlotte, NC, expanded its operations and opened an office in Charleston. The company...
PatsPlaceBBQ

BBQ for a Great Cause | Supporting Pat’s Place Child Advocacy Center

BBQ & Blue Jeans is the party of the summer and the signature annual fundraising event for Pat’s Place Child...