Project Update: May 2014
Monthly Project Status:
Construction Highlights Last 30 Days
Work Completed this month:
- Completed pond
- Completed Demolition of exterior wall and tie in to new building
- Installation of TPO Roof
- Framing & Drywall Installation in office
- Prime Exterior and Interior walls
- Rough in of all MEP
- Install Sprinkler Pipe
- Concrete Pavement and ramp at Docks
- Misc Concrete (Dolly Pads and Curbs)
- Installation dock equipment
Monthly Photo Highlights include:
- Completion of Pond
- Demolition of Exterior Wall and Tie-In to New Structure
- Completion of Demolition of Exterior Wall
- Office Framing and Drywall Installation
- Pavement Installation at Docks
- Curb and Gutter Installation
- Dock Equipment Installation