Project Update: May 2014

Monthly Project Status:

Construction Highlights Last 30 Days

Work Completed this month:

  • Completed pond
  • Completed Demolition of exterior wall and tie in to new building
  • Installation of TPO Roof
  • Framing & Drywall Installation in office
  • Prime Exterior and Interior walls
  • Rough in of all MEP
  • Install Sprinkler Pipe
  • Concrete Pavement and ramp at Docks
  • Misc Concrete (Dolly Pads and Curbs)
  • Installation dock equipment

Monthly Photo Highlights include:

  • Completion of Pond

Completion-of-Pond_853x640

  • Demolition of Exterior Wall and Tie-In to New Structure

Demolition-of-exterior-wall-and-tie-in-to-new-structure_853x640

  • Completion of Demolition of Exterior Wall

Exterior-Wall-Demolition-Complete_853x640

  • Office Framing and Drywall Installation

Office-Framing-&-Drywall-Installation_640x640

  • Pavement Installation at Docks

Pavement-Installation-at-Docks_480x640

  • Curb and Gutter Installation

Curb-&-gutter640x640

  • Dock Equipment Installation

 

Dock-Equipment-Installationz_480x640

Share This

Quick Links

In the News


Live Feed: CMPD Central Division Facility

Live Feed: CMPD Central Division Facility

Follow along with the construction progress, via recent snapshot or a time-lapse, at Charlotte-Mecklenburg Police Department’s new Central Division Facility.
Huber_Technology_groundbreaking

Wastewater equipment manufacturer breaks ground on new HQ in Charlotte region

Look for Huber Technology Inc. to open its relocated headquarters in Lincoln County by early 2020 or potentially earlier —...
Edifice continues its support of Covenant Day and the ContainIt Project

Edifice continues its support of Covenant Day and the ContainIt Project

Edifice continues its support of Covenant Day as a key sponsor of their annual Sustainability Sporting Clay Shoot benefiting the ContainIt...