Project Update: May 2014

Monthly Project Status:

Construction Highlights Last 30 Days

Work Completed this month:

  • Completed pond
  • Completed Demolition of exterior wall and tie in to new building
  • Installation of TPO Roof
  • Framing & Drywall Installation in office
  • Prime Exterior and Interior walls
  • Rough in of all MEP
  • Install Sprinkler Pipe
  • Concrete Pavement and ramp at Docks
  • Misc Concrete (Dolly Pads and Curbs)
  • Installation dock equipment

Monthly Photo Highlights include:

  • Completion of Pond

Completion-of-Pond_853x640

  • Demolition of Exterior Wall and Tie-In to New Structure

Demolition-of-exterior-wall-and-tie-in-to-new-structure_853x640

  • Completion of Demolition of Exterior Wall

Exterior-Wall-Demolition-Complete_853x640

  • Office Framing and Drywall Installation

Office-Framing-&-Drywall-Installation_640x640

  • Pavement Installation at Docks

Pavement-Installation-at-Docks_480x640

  • Curb and Gutter Installation

Curb-&-gutter640x640

  • Dock Equipment Installation

 

Dock-Equipment-Installationz_480x640

Share This

Quick Links

In the News


Play Button Eastway Recreation Center Project Update | September 2019

Eastway Recreation Center Project Update | September 2019

Another Eastway project update for you! Not that we’re biased, but it’s looking 💯
Pastors Masters 2019 at The Club at Longview

Pastors Masters 2019 at The Club at Longview

This year’s tournament got off to a chilly start as we returned back to The Club at Longview and the...
Edifice_Oktoberfeier_2019

Prost to our 2019 Fall Party | Oktoberfeier!

Fall is officially here and we celebrated the change of seasons with our annual German festival, Oktoberfeier. Saturday, September 28...