Project Update: May 2014
Monthly Project Status: [pl_blockquote cite= “Update for May 2014”] Construction Highlights Last 30 Days:
Area C
- Retaining Wall Footing & Wall
- Foundation Drain & Backfill Wall
- Waterproofing Foundation Wall
- Mechanical Piping In Basement (90% complete)
- Exterior Framing & Sheathing
- Curtainwall & Glazing (90% complete)
Area D
- Plenum Area Footings
- Structural Steel For First Floor Seating (35% complete)
- Masonry Around Stage
- Masonry At House To Roof (75% complete)
- Courtyard Wall Sheathing (95% complete)
- Stair C/D Sheathing
- Stair F Framing (90% complete)
- Curtainwall/Glazing In Lobby (75% complete)
- All Elevated Concrete Balcony Slabs
Area A
- Roofing At Classroom
- Exterior Wall Framing/Sheathing Courtyard (90% complete)
- Exterior Wall Framing At South (25% complete)
- Interior Wall Framing (65% complete)
- Sprinkler Overhead Install (50% complete)
- Curtainwall At South Elevation (75% complete)
Area B
- Slab On Grade (65% complete)
- Masonry (50% complete)
- Electrical Underground Rough In
- Plumbing Underground Rough In
- Setting Mechanical Equipment (80% complete)
[/pl_blockquote] Monthly Photo Highlights include:
- North Exterior:
- Area B – Slab On Grade:
- East Exterior:
- Structural Steel For First Floor Seating:
- South Exterior:
- Aerial Overview: May 4th, 2014
Visit our Ox Blue Site to play time lapse construction through March 2014: http://oxblue.com/open/edifice/all