Monthly Project Status:

Construction Highlights Last 30 Days:

Area C

  • Retaining Wall Footing & Wall
  • Foundation Drain & Backfill Wall
  • Waterproofing Foundation Wall
  • Mechanical Piping In Basement (90% complete)
  • Exterior Framing & Sheathing
  • Curtainwall & Glazing (90% complete)

Area D

  • Plenum Area Footings
  • Structural Steel For First Floor Seating (35% complete)
  • Masonry Around Stage
  • Masonry At House To Roof  (75% complete)
  • Courtyard Wall Sheathing (95% complete)
  • Stair C/D Sheathing
  • Stair F Framing (90% complete)
  • Curtainwall/Glazing In Lobby (75% complete)
  • All Elevated Concrete Balcony Slabs

Area A

  • Roofing At Classroom
  • Exterior Wall Framing/Sheathing Courtyard  (90% complete)
  • Exterior Wall Framing At South (25% complete)
  • Interior Wall Framing  (65% complete)
  • Sprinkler Overhead Install (50% complete)
  • Curtainwall At South Elevation (75% complete)

Area B

  • Slab On Grade (65% complete)
  • Masonry (50% complete)
  • Electrical Underground Rough In
  • Plumbing Underground Rough In
  • Setting Mechanical Equipment (80% complete)
Update for May 2014

Monthly Photo Highlights include:

  • North Exterior:

North-Exterior1024x768

  • Area B – Slab On Grade:

Area-B-Slab-On-Grade_1024x768

  • East Exterior:

East-Exterior_1024x768

  • Structural Steel For First Floor Seating:

First-Floor-Seating-Steel_1024x768

  • South Exterior:

South-Exterior_1024X768

  • Aerial Overview:  May 4th, 2014

Aerial.May14.DSC_0582_1024x768
Visit our Ox Blue Site to play time lapse construction through March 2014: http://oxblue.com/open/edifice/all