Project Update: May 2015

A list of the project’s milestones and action items that have been completed within the last 30 days for the CFCC Humanities and Fine Arts Center project.

Construction Highlights Last 30 Days: CFCC

[pl_blockquote cite= “Update for May 2015”]

  • Completed VCT
  • Final Paint A/B Classrooms 100%
  • Theater Seating Completed
  • Ceiling Tile in Lobby 100%
  • Above Ceiling Inspections in SLLs 50%
  • Fabric Walls 95%
  • Hanging Drywall in Area D 95%
  • Louver Install 100%

[/pl_blockquote]Monthly Photo Highlights Include:

Click on the photos below to view the full photo. [hover category=”CFCCBlog_May”] 

Share This

Quick Links

Stay on top industry news with edifice

Business North Carolina Announced Mid-Market Fast 40

Business North Carolina Announced Mid-Market Fast 40

EDIFICE ranked #5  Forty fast-growing North Carolina middle-market companies were celebrated for their entrepreneurial spirit and strong revenue growth this...
Groundbreaking for the new Jennings Park

Groundbreaking for the new Jennings Park

Statesville, N.C. — Friday, July 28 marked the groundbreaking ceremony for the new Jennings Park for Iredell County along with...
EDIFICE Elevates supports Dilworth Soup Kitchen

EDIFICE Elevates supports Dilworth Soup Kitchen

During the month of June, EDIFICE Elevates partnered with Dilworth Soup Kitchen and delivered a truckload of groceries and canned...