Project Update: May 2015

A list of the project’s milestones and action items that have been completed within the last 30 days for the CFCC Humanities and Fine Arts Center project.

Construction Highlights Last 30 Days: CFCC

[pl_blockquote cite= “Update for May 2015”]

  • Completed VCT
  • Final Paint A/B Classrooms 100%
  • Theater Seating Completed
  • Ceiling Tile in Lobby 100%
  • Above Ceiling Inspections in SLLs 50%
  • Fabric Walls 95%
  • Hanging Drywall in Area D 95%
  • Louver Install 100%

[/pl_blockquote]Monthly Photo Highlights Include:

Click on the photos below to view the full photo. [hover category=”CFCCBlog_May”] 

Share This

Quick Links

In the News


Simpsonville Municipal Complex Groundbreaking

Simpsonville Municipal Complex Groundbreaking

Simpsonville, S.C. — The City of Simpsonville broke ground on Thursday on its new municipal complex in a ceremony onsite....
German manufacturer, H-T-L perma USA LP, breaks ground on new US  Headquarters in Charlotte

German manufacturer, H-T-L perma USA LP, breaks ground on new US Headquarters in Charlotte

Company is expanding manufacturing operations and moving to a new campus in Steele Creek. CHARLOTTE, N.C. (February 21, 2023) –...
Celebrating our Partners in Cajun Style

Celebrating our Partners in Cajun Style

Edifice held its annual Mardi Gras-themed subcontractor soiree on Fat Tuesday, February 21, 2023 at Lenny Boy Brewing in honor...