Project Update: May 2015

A list of the project’s milestones and action items that have been completed within the last 30 days for the CFCC Humanities and Fine Arts Center project.

Construction Highlights Last 30 Days: CFCC

[pl_blockquote cite= “Update for May 2015”]

  • Completed VCT
  • Final Paint A/B Classrooms 100%
  • Theater Seating Completed
  • Ceiling Tile in Lobby 100%
  • Above Ceiling Inspections in SLLs 50%
  • Fabric Walls 95%
  • Hanging Drywall in Area D 95%
  • Louver Install 100%

[/pl_blockquote]Monthly Photo Highlights Include:

Click on the photos below to view the full photo. [hover category=”CFCCBlog_May”] 

Share This

Quick Links

In the News


Live Feed: Hopewell Baptist Phase III – New Sanctuary

Live Feed: Hopewell Baptist Phase III – New Sanctuary

Watch the exciting construction progress of the Hopewell Baptist Church’s new Sanctuary from our live webcam. See what’s happening on-site...
Accredited Quality Contractor

Edifice is Committed to Providing the Highest Quality Construction Services

Edifice is committed to providing its clients with the highest quality construction services and is pleased to announce that its...
Supporting Pat’s Place for the Children of Mecklenburg County

Supporting Pat’s Place for the Children of Mecklenburg County

We are pleased to begin a multi-year sponsorship with Pat’s Place Child Advocacy Center. Earlier this year we announced our...