Project Update: September 2014

Construction Highlights Last 30 Days:

  • House Roofing Complete
  • Proscenium Wall Framing & Finishing Complete
  • Sound Reflector Finishing & Painting Complete
  • Dryfall In House Area 90%
  • Exterior Framing Around Lobby Roof Complete
  • Glazing Curtainwall In Lobby 100%
  • Hanging Drywall Area A
  • Hanging/Finishing Drywall Area C Sound Walls
  • Roofing On Stairs C/D/F
  • Monumental Stair In Lobby Complete
  • Underground Rough In At Courtyard 100%
  • Air Handling Units Ready To Start

Monthly Photo Highlights Include:

Elevator 1 & 2Elevator-1-&-2

 

Framing on Bottle Opener
Framing-On-Bottle-Opener

 

Monumental Stair Installation
Monumental-Stair-Install

 

South Entrance Storefront
South-Entrance-Storefront

 

West Wall Progress
West-Wall-Progress

 

Project Aerial:  September 15, 2014 SeptemberAerial

Share This

Quick Links

In the News


Play Button CrossRidge Building One | February 2021

CrossRidge Building One | February 2021

The CrossRidge Office Building One is moving right along! This month’s video features finalizing the slab finish after a morning...
EDIFICE Promotes Gaius Carter to Project Executive

EDIFICE Promotes Gaius Carter to Project Executive

EDIFICE is pleased to announce that Gaius Carter has been promoted to Project Executive focusing on the manufacturing sector. Gaius has...
The John Crosland School Takes Learning in a New Direction

The John Crosland School Takes Learning in a New Direction

EDIFICE, along with a group of great partners, helped bring the John Crosland School’s outdoor pavilion to life.  Watch how...