Construction Highlights Last 30 Days:

  • House Roofing Complete
  • Proscenium Wall Framing & Finishing Complete
  • Sound Reflector Finishing & Painting Complete
  • Dryfall In House Area 90%
  • Exterior Framing Around Lobby Roof Complete
  • Glazing Curtainwall In Lobby 100%
  • Hanging Drywall Area A
  • Hanging/Finishing Drywall Area C Sound Walls
  • Roofing On Stairs C/D/F
  • Monumental Stair In Lobby Complete
  • Underground Rough In At Courtyard 100%
  • Air Handling Units Ready To Start
Update for August 2014

Monthly Photo Highlights Include:

Elevator 1 & 2Elevator-1-&-2

 

Framing on Bottle Opener
Framing-On-Bottle-Opener

 

Monumental Stair Installation
Monumental-Stair-Install

 

South Entrance Storefront
South-Entrance-Storefront

 

West Wall Progress
West-Wall-Progress

 

Project Aerial:  September 15, 2014 SeptemberAerial