Project Update: September 2014

Construction Highlights Last 30 Days:

  • House Roofing Complete
  • Proscenium Wall Framing & Finishing Complete
  • Sound Reflector Finishing & Painting Complete
  • Dryfall In House Area 90%
  • Exterior Framing Around Lobby Roof Complete
  • Glazing Curtainwall In Lobby 100%
  • Hanging Drywall Area A
  • Hanging/Finishing Drywall Area C Sound Walls
  • Roofing On Stairs C/D/F
  • Monumental Stair In Lobby Complete
  • Underground Rough In At Courtyard 100%
  • Air Handling Units Ready To Start

Monthly Photo Highlights Include:

Elevator 1 & 2Elevator-1-&-2

 

Framing on Bottle Opener
Framing-On-Bottle-Opener

 

Monumental Stair Installation
Monumental-Stair-Install

 

South Entrance Storefront
South-Entrance-Storefront

 

West Wall Progress
West-Wall-Progress

 

Project Aerial:  September 15, 2014 SeptemberAerial

Share This

Quick Links

In the News


Live Feed: CMPD Central Division Facility

Live Feed: CMPD Central Division Facility

Follow along with the construction progress, via recent snapshot or a time-lapse, at Charlotte-Mecklenburg Police Department’s new Central Division Facility.
Huber_Technology_groundbreaking

Wastewater equipment manufacturer breaks ground on new HQ in Charlotte region

Look for Huber Technology Inc. to open its relocated headquarters in Lincoln County by early 2020 or potentially earlier —...
Edifice continues its support of Covenant Day and the ContainIt Project

Edifice continues its support of Covenant Day and the ContainIt Project

Edifice continues its support of Covenant Day as a key sponsor of their annual Sustainability Sporting Clay Shoot benefiting the ContainIt...