Project Update: September 2014

Construction Highlights Last 30 Days:

  • House Roofing Complete
  • Proscenium Wall Framing & Finishing Complete
  • Sound Reflector Finishing & Painting Complete
  • Dryfall In House Area 90%
  • Exterior Framing Around Lobby Roof Complete
  • Glazing Curtainwall In Lobby 100%
  • Hanging Drywall Area A
  • Hanging/Finishing Drywall Area C Sound Walls
  • Roofing On Stairs C/D/F
  • Monumental Stair In Lobby Complete
  • Underground Rough In At Courtyard 100%
  • Air Handling Units Ready To Start

Monthly Photo Highlights Include:

Elevator 1 & 2Elevator-1-&-2

 

Framing on Bottle Opener
Framing-On-Bottle-Opener

 

Monumental Stair Installation
Monumental-Stair-Install

 

South Entrance Storefront
South-Entrance-Storefront

 

West Wall Progress
West-Wall-Progress

 

Project Aerial:  September 15, 2014 SeptemberAerial

Share This

Quick Links

In the News


Play Button The Square at South End | September 2020

The Square at South End | September 2020

The Square at South End continues to impress. The parking deck structure is complete and the site cleared around it...
Charleston Team

Edifice Expands to Charleston

Edifice, the regional general contractor headquartered in Charlotte, NC, expanded its operations and opened an office in Charleston. The company...
PatsPlaceBBQ

BBQ for a Great Cause | Supporting Pat’s Place Child Advocacy Center

BBQ & Blue Jeans is the party of the summer and the signature annual fundraising event for Pat’s Place Child...