Project Update: September 2014
Construction Highlights Last 30 Days:
- House Roofing Complete
- Proscenium Wall Framing & Finishing Complete
- Sound Reflector Finishing & Painting Complete
- Dryfall In House Area 90%
- Exterior Framing Around Lobby Roof Complete
- Glazing Curtainwall In Lobby 100%
- Hanging Drywall Area A
- Hanging/Finishing Drywall Area C Sound Walls
- Roofing On Stairs C/D/F
- Monumental Stair In Lobby Complete
- Underground Rough In At Courtyard 100%
- Air Handling Units Ready To Start
Monthly Photo Highlights Include: