Project Update: March 2014

Monthly Project Status: Construction Highlights Last 30 Days Fire line/hydrant installation Prep & pour footings Completed footings and stone for…

Childress Klein YMCA

Charlotte, North Carolina ABOUT Extensive renovations  were completed on this uptown YMCA branch located in One Wells Fargo Center. Updates…

Elevation Church | Lake Norman Campus

ABOUT This 41,600 square foot, $5 million renovation included the tranformation a cineplex into a state-of-the art worship center in…

Project Update: March 2014

Monthly Project Status: Construction Highlights Last 30 Days Roofing On The Lobby Area Completion Of Precast Panels Start Of Curtainwall/Storefront…

Project Update: February 2014

Monthly Project Status: Construction Highlights Last 30 Days Erosion Control: In place and inspected Demolition: Asphalt Milling, Curb & Gutter…

Project Update: February 2014

Monthly Project Status: Construction Highlights Last 30 Days Precast Panel Start (Photo from Precast Ceremony) Structural Steel Substantially Complete In…

Project Update: December 2013

Monthly Project Status: Progress photos of this month’s construction milestones • Area B Steel Erection • Air Handling Unit Set In Basement…

Project Update: November 2013

Monthly Project Status: Progress photos of this month’s construction milestones Monthly Highlights include: • The “bottle opener” photo, a significant feature…

Project Update: October 2013

Monthly Project Status:

  • Basement Slab On Grade Just Poured
  • Prepping Slab On Deck Under The Second Floor Balcony Seating
  • Sound Deflectors Above Stage Being Installed
  • Spray Fireproofing Installed On C Building
  • Spray Fireproofing On Second Floor Steel
  • Steel Erection At North Side Of Lobby Area Behind The House

 

Poplin Road Elementary

Indian Trail, North Carolina About This 13.2 million, 98,000 square foot new elementary school sits on a 35-acre site in…