Project Update: August 2014

Construction Highlights Last 30 Days: Completed Glazing the Storefront West Elevation Completed Masonry on North Elevation Closed Masonry Access Completed…

Project Update: July 2014

Construction Highlights Last 30 Days: Area C Completed Glazing the Storefront West Elevation Close to Completing the MEPS Wall Rough In…

Project Update: June 2014

Construction Highlights Last 30 Days: Area C Brick Veneer (95% complete) Storefront on West Elevation (65% complete) Insulating Precast Panels…

30-Day Look Ahead

Work to be performed in the next 30 days: Finishes at the Office Upfit Final Paint VCT / Carpet Tile…

Project Update: May 2014

Monthly Project Status: Construction Highlights Last 30 Days Work Completed this month: Completed pond Completed Demolition of exterior wall and…

UNC Charlotte Belk Residence Hall

Charlotte, North Carolina About The 178,000 square foot, 426-bed upper class residence hall facility includes both four (4) bedroom apartments…

CaroMont Health

Gastonia, North Carolina ABOUT CaroMont Courtview Medical Office Building Upfit 16,000sf renovation to existing doctor’s offices. Work included new exam, trauma,…

Off Broadway Shoe Warehouse Corporate Headquarters

Edifice, Inc. served as general contractor on this four-story, 76,000-square foot corporate headquarters office and lobby addition. The addition included Class-A office space, lounge area, balcony, and back patio. The project included parking lot expansion and over three acres of site improvements.  The facility doubled the headquarters’ current square footage and involved relocating the headquarters from the Atlanta area to Charlotte.

Project Update: May 2014

Monthly Project Status: [pl_blockquote cite= “Update for May 2014”] Construction Highlights Last 30 Days: Area C Retaining Wall Footing & Wall…

Project Update: April 2014

Monthly Project Status: [pl_blockquote cite= “Update for April 2014”] Construction Highlights Last 30 Days Work Completed this month: Parking Lot…