Right Direction International “Kids Town”

Kids Town is a one story addition to the exisiting Family Life Center which Edifice built in 2008.

Christ Covenant Church | February 2016

Project Update: Since our last blog post we have completed structural steel, installed a roof, installed all HVAC units on…

Covenant Day School | February 2016

Project Update: The Covenant Day School’s new high school project continues to move right along and on schedule. Since our last blog,…

Covenant Day School | November 2015

The Covenant Day School’s new high school building is really starting to take shape. The past 30 days we focused heavily on the steel erection process.

Christ Covenant Church | November 2015

Despite the record rainfall amounts on the Christ Covenant site, we managed to get several key things in place, including the elevator pit, surrounding walls, and the lower level slab. We finally completed backfilling on the north side of the lower level last week.

Christ Covenant Church | October 2015

Project Update: In between the rain events this past month at the Christ Covenant Church site, we have worked primarily…

Covenant Day School | October 2015

Project Update: On site at the Covenant Day School, we have completed all of the building footings and the retaining…

Christ Covenant Church | September 2015

Project Update: Good progress has been made over the last few weeks with the Christ Covenant’s Community Life Center. After excavation…

Covenant Day School | September 2015

Project Update: The Covenant Day School’s new High School has seen steady progress this month, which mainly includes underground storm and…

Covenant Day School | August 2015

Project Update: With the start of school just around the corner, we are working hard to get the Covenant Day…