University Recreation Center | December 2017

We wrapped up the end of the year with the UNC Charlotte University Recreation Center project continuing to show progress. As the concrete trade contractor continued their installation of concrete foundations and retaining walls at the first floor level, they also began work on the second floor of the building. Walls are being waterproofed and prepped for backfill operations. Concrete columns at the west side of the building are also being constructed for the post tension concrete superstructure at the Natatorium/Gym area. Under-slab utility work has begun at the first floor, with the first slab on grade pour scheduled for mid-January. Site work trade contractor is continuing with the installation of underground site storm and sanitary sewer systems.

The RailYard is Underway in Charlotte’s South End

Beacon Partners has teamed with Edifice and RBA Group for the design and construction services for its RailYard project located…

Metrolina Park | December 2017

In this video you will see the progression of Building 5’s building pad. This 350,000sf foundation is being constructed in…

Iredell County’s new Public Safety Complex is Underway

Edifice and ADW Architects are pleased to provide design-build services for Iredell County’s new public safety complex. The team will provide…

Grand Opening Celebration

Looks like everyone had a blast at the Grand Opening Celebration of Gaston County Family YMCA‘s Warlick Family YMCA on Sunday!

University Recreation Center | November 2017

During the month of November, work at the UNC Charlotte University Recreation Center project continues to progress with the concrete trade contractor continuing their installation of concrete foundations and retaining walls at the first floor level of the building. They have also started working their way up the hill to complete a portion of the 2nd floor foundations and retaining walls. Under-slab utility work at the first floor is scheduled to begin mid-December. Site work trade contractor is continuing with the installation of underground site storm and sanitary sewer systems.

Metrolina Park | November 2017

Transformation continues as we prepare the building pad for Building #5 of Phase 2. With the footings completed and the…

University Recreation Center | October 2017

During the month of October, work at the UNC Charlotte Health and Wellness Center Project continues to progress on schedule with the Concrete trade contractor beginning their installation of concrete foundations and retaining walls at the first floor level of the building. They will continue with this work at the first floor into the month of November as they move across the building, which will allow areas to be freed up for other trades to begin under slab utility work shortly. The majority of trench rock previously impeding concrete foundation installation along the first floor retaining wall has now been removed. Site Work trade contractor has proceeded and is continuing with installation of underground storm and sanitary systems at the west side of the site.

Metrolina Park | October 2017

Edifice continues to oversee the construction of the distribution park, named Metrolina Park. Developed by Beacon Partners and designed by…

Charlotte East Language Academy | October 2017

Lots of progress at Charlotte Mecklenburg Schools’ newest K-8 school, Charlotte East Language Academy – look at that beautiful field!